COGIS - Conditions of Approval Results
TypeSource DocumentConditions of Approval
EngineerForm: (04)
402617944
03/09/2021
1. Operator will implement measures to control venting, to protect health and safety, and to ensure that vapors and odors from well operations do not constitute a nuisance or hazard to public welfare. 2. This well is scheduled to be plugged in 2022. Operator will continue to manage, monitor and mitigate pressures for this well. A Form 4 bradenhead plan report of work done will be submitted within 30 days of 03/04/2022. The sundry should include monthly pressure monitoring data, flow rate information, sample analysis interpretation, and bradenhead test description. 3. Shut in bradenhead pressure shall not exceed 50 psig.
EngineerForm: (04)
402617944
03/09/2021
Prior to starting bradenhead abatement, if a sample has not been collected within the last twelve months collect bradenhead and production gas samples for laboratory analysis. Sampling will comply with Operator Guidance - Bradenhead Testing and Reporting Instructions, Appendix A: Liquid and Gas Sampling. Copies of all final laboratory analytical results will be provided to the COGCC within three months of collecting the samples.
EngineerForm: (04)
402943939
02/22/2022
1. Operator will implement measures to control venting, to protect health and safety, and to ensure that vapors and odors from well operations do not constitute a nuisance or hazard to public welfare. 2. Well to plugged no later than 12/31/2022. Pressure is to be managed and mitigated until plugging is complete. Summary of well monitoring and mitigation will be submitted on a Form 4 Sundry within 30 days of the well being plugged and abandoned but no later than 12/31/2022. The sundry should include monthly pressure monitoring data, flow rate information, sample analysis interpretation, and bradenhead test description. 3. Shut in bradenhead pressure shall not exceed 50 psig.
OGLAForm: (04)
403100773
07/19/2022
Operator will implement measures to capture, combust, or control emissions to protect health and safety, and to ensure that vapors and odors from well completion(s), well repair/maintenance, well perforating, temporary abandonment activities, additional equipment installation, and/or testing operations with a workover rig, wireline rig, or other heavy equipment do not constitute a nuisance or hazard to public health, welfare and the environment. Due to proximity of building units (BUs) all blowdown gases will be controlled.
EngineerForm: (04)
403100773
08/01/2022
1) Provide electronic Form 42 Notice of MIRU 2 business days ahead of operations. 2) The additional cement referenced shall be placed as indicated. The placed cement shall be verified with a CBL and documented with a Form 5 within 30 days of repair operations. 3) Operator will successfully pressure test the production casing. Pressure test to be submitted on Form 21 within 30 days of the pressure test.
EngineerForm: (04)
403280789
01/12/2023
Operator shall continue to monitor pressure, and report to COGCC through annual testing. If monitored well conditions meet the thresholds defined by Order 1-232 a new bradenhead test and sundry must be filed.
EngineerForm: (04)
403293331
01/20/2023
Operator shall continue to monitor pressure, and report to COGCC through annual testing. If monitored well conditions meet the thresholds defined by Order 1-232 a new bradenhead test and sundry must be filed.
 
COGIS - Best Management Practice Results
BMP TypeSource DocumentBest Management Practices
PlanningForm: (04 )
403100773
8/1/2022
Operations are daylight-only; no lighting impacts are anticipated from operations.
Community Outreach and NotificationForm: (04 )
403100773
8/1/2022
Signs will be placed in conspicuous locations and will include Oxy contact information; the Oxy Stakeholder Relations team will respond to all community member inquiries. The signs will be placed so as not to create a potential traffic hazard
Community Outreach and NotificationForm: (04 )
403100773
8/1/2022
Courtesy notifications will be sent to all parcel owners with building units within 1,500 feet of the location letting them know about our subsequent well operations and providing contact information for Kerr McGee’s response line and online resources.
WildlifeForm: (04 )
403100773
8/1/2022
This planned location is located near potential burrowing owl habitat. If operations are planned between 3/15 – 8/31, field surveys will be conducted to confirm the presence of suitable habitat. If habitat is confirmed, field surveys following CPW protocol will be conducted to assess the presence or absence of burrowing owls. If burrowing owls are determined to be present and work cannot be delayed, HSE will consult with CPW prior to operations beginning.
Dust controlForm: (04 )
403100773
8/1/2022
Water will be placed on dirt access roads to mitigate dust as needed.
Noise mitigationForm: (04 )
403100773
8/1/2022
Operations will be in compliance with Table 423-1 requirements. Based off the rig sound signature, rig orientation will be considered to reduce noise levels to nearby building units.
Odor mitigationForm: (04 )
403100773
8/1/2022
Closed, upright tanks are being utilized to mitigate odor.