Engineer | Form: (04 ) 403247357 12/13/2022 | TA/Observation Well COAs
1)Complete MITs and regulatory requirements as required for Observation Wells
2)The Form 7 reporting must reflect the well status
3)A Form 5A is required to report all plugs currently downhole which isolate the perforated interval.
|
Engineer | Form: (04 ) 403869927 7/30/2024 | 1) For applicable operations, submit a Form 5 within 30 days of the work with job related documents including a minimum of one of the following attachments: operations summary, cement job summary and/or wireline summary. Additionally, include CBL’s and any additional logs run. |
OGLA | Form: (04 ) 403869927 7/30/2024 | Due to proximity to a wetland, surface water and expected shallow groundwater, operator will use secondary containment for all tanks and other liquid containers. Operator will implement stormwater BMPs and erosion control measures as needed to prevent sediment and stormwater runoff from entering the wetland and surface water.
LAS review complete. |