Engineer | Form: (04 ) 402792503 8/31/2021 | 1) This sundry to conduct bradenhead diagnostic evaluations is valid until 1/27/2022
2) For Wells that have sustained casing pressure above the action threshold as determined through diagnostic testing and evaluation, the Operator will provide a PMP with the Form 4, including a description of the Operator’s findings from the previous year, number of times the well was blown down, a current WBD and future plans for more frequent monitoring or testing, pressure mitigation, or remedial well work by 1/27/2022
3) Submit the gas sample analysis from previous Form 17 bradenhead test on a Form 43
4) Comply with any CDPHE, Air Pollution Control Division rules or requirements for all atmospheric discharges.
|
Engineer | Form: (04 ) 402936375 1/27/2022 | 1. Operator shall comply with COGCC Rule 419 Bradenhead Monitoring, Testing, and Reporting and Rule 420 Form 17, Bradenhead Test Report
2. If BH pressure exceeds 225 psi complete a Form 17 and submit a BHP Sundry with mitigation plans |