Engineer | Form: (04 ) 402068351 6/11/2019 | 1)The Operator shall monitor the bradenhead pressure of the proposed well and all offset wells under Operator’s control which penetrate the injection target formation and have a treated interval separation of 300 feet or less. Operator shall notify COGCC Engineering staff if bradenhead pressures increase by more than 200 psig. |
UIC | Form: (04 ) 402068351 7/11/2019 | New packer must be placed within 100 ft of top perforation @ 6615 ft. Contact COGCC to discuss plan modification if this is not feasible. |
OGLA | Form: (06 ) 402975039 3/15/2022 | Operator will implement measures to capture, combust, or control emissions to protect health and safety, and to ensure that vapors and odors from well plugging operations do not constitute a nuisance or hazard to public health, welfare and the environment. |
Engineer | Form: (06 ) 402975039 4/14/2022 | 1) Provide electronic Form 42 Notice of MIRU 2 business days ahead of operations and electronic Form 42 Notice of Plugging Operations 48 hours prior to mobilizing for plugging operations.
2) The approved Form 6, Notice of Intent will be at the location during all phases of plugging operations.
3) Operator shall implement measures to control venting and to ensure that vapors and odors from well plugging operations do not constitute a nuisance or hazard.
4) Properly abandon flowlines as per Rule 1105. Pursuant to Rule 911.a. Closure of Oil and Gas Facilities, Operator will submit Site Investigation and Remediation Workplans via Form 27 for COGCC prior approval before cutting and capping the plugged well, conducting flowline abandonment, and removing production equipment. Pursuant to Rule 1105.f. Abandonment Verification, within 90 days of an operator completing abandonment requirements for a flowline or crude oil transfer line, an operator must submit a Field Operations Notice, Form 42-Abandonment of Flowlines for on-location flowlines, and a Flowline Report, Form 44, for off-location flowlines or crude oil transfer lines.
5) Perform bradenhead test prior to MIRU if test has not been performed within six months of plugging. Submit results on Form 17. Contact area environmental protection specialist for sampling and analysis requirements if initial bradenhead pressure is greater than 25 psi.
6) This well has federal minerals. Operator shall notify COGCC engineering staff of any plugging changes required by the BLM or unexpected conditions in the field as soon as feasible. Primary contact is Aaron Katz at 970-765-6300. Alternate COGCC contact is Craig Burger at 970-319-4194.
|
UIC | Form: (04 ) 402950077 1/5/2023 | This Sundry is a follow up for the Operator's intent to abandon the field. The Sundry was filed timely, but new Financial Assurance Rules have taken effect. Operator must abide by the plugging date of 12/31/2028. |
OGLA | Form: (06 ) 403776089 5/9/2024 | Operator provided COAs:
3rd party wildlife surveys will be conducted on this well prior to rigging up for P&A activities. Should sensitive HPH conditions be identified during the screening process, Chevron will delay the work until conditions (nesting) clear and/or consult directly with CPW for guidance and discussion of potential mitigation measures that may be incorporated.
Notification will be given to any adjacent building unit occupants within a 1000 feet of the wellhead of planned P&A start date. |
Engineer | Form: (06 ) 403776089 6/5/2024 | 1) Provide electronic Form 42 Notice of MIRU 2 business days ahead of operations and electronic Form 42 Notice of Plugging Operations 48 hours prior to mobilizing for plugging operations. These are two separate notifications, required by Rules 405.e and 405.l.
2) The approved Form 6, Notice of Intent will be at the location during all phases of plugging operations.
3) Operator shall implement measures to control venting and to ensure that vapors and odors from well plugging operations do not constitute a nuisance or hazard.
4) Prior to placing surface shoe plug verify that all fluid (liquid and gas) migration has been eliminated. If evidence of fluid migration or pressure remains, contact ECMC Engineer for an update to plugging orders.
5) If applicable properly abandon flowlines as per Rule 1105. Pursuant to Rule 911.a. Closure of Oil and Gas Facilities, Operator will submit Site Investigation and Remediation Work plans via Form 27 for ECMC prior approval before cutting and capping the plugged well, conducting flowline abandonment, and removing production equipment. Pursuant to Rule 1105.f. Abandonment Verification, within 90 days of an operator completing abandonment requirements for a flowline or crude oil transfer line, an operator must submit a Field Operations Notice, Form 42-Abandonment of Flowlines for on-location flowlines, and a Flowline Report, Form 44, for off-location flowlines or crude oil transfer lines.
6) Prior to starting plugging operations a bradenhead test shall be performed if there has not been a reported bradenhead test within the 60 days immediately preceding the start of plugging operations.
If, before opening the bradenhead valve, the beginning pressure is greater than 25 psi, sampling is required.
If pressure remains at the conclusion of the test, or if any liquids were present during the test, sampling is required.
The Form 17 shall be submitted within 10 days of the test. Sampling shall comply with Operator Guidance - Bradenhead Testing and Reporting Instructions. If samples are collected, copies of all final laboratory analytical results shall be provided to the ECMC within three (3) months of collecting the samples.
7) With the Form 6 SRA operator must provide written documentation, which positively affirms each COA listed above has been addressed.
8) This well has federal minerals. Operator shall notify ECMC engineering staff of any plugging changes required by the BLM or unexpected conditions in the field as soon as feasible. Primary contact is Aaron Katz at 970-765-6300. Alternate ECMC contact is Byron Gale at 970-319-4194.
|