WELL05-005-07269POWELL
5-64 15-16-1CHZ
TRUE OIL LLC
90450
PR
8/1/2023
WILDCAT
99999
ARAPAHOE  005
NESE 15 5S64W 6
449920View Related
 
COGIS - Conditions of Approval Results
TypeSource DocumentConditions of Approval
EngineerForm: (02 )
401131578
4/4/2017
Operator acknowledges the proximity of the listed non-operated wells. Operator assures that this offset list will be remediated per the DJ Basin Horizontal Offset Policy (option 4). Operator will submit a Form 42 (“OTHER – AS SPECIFIED BY PERMIT CONDITION”) stating that appropriate mitigation will be completed, prior to the hydraulic stimulation of this well. This Form 42 shall be filed 48 hours prior to stimulation. Operator will assure that the well is either properly plugged and abandoned or a plug is placed within 100’ of the Niobrara perfs and the production casing actively monitored for any pressure during the stimulation treatment – if 200# or more of pressure is observed during stimulation, the treatment will be suspended until it can be determined that the pressure can be successfully bled off without a spill or opened to a tank and allowed to flow. STATE B 1 (API # 005-06660)
EngineerForm: (02 )
401131578
4/4/2017
Operator acknowledges the proximity of the listed non-operated wells. Operator assures that this offset list will be remediated per the DJ Basin Horizontal Offset Policy (option 3) and ensure all applicable documentation is submitted. Operator will submit a Form 42 (“OFFSET MITIGATION COMPLETED”) stating what appropriate mitigation occurred and that it has been completed, prior to the hydraulic stimulation of this well. HUSKY ET AL-STATE 2-16 (API # 005-06685); SMOKEY HILL-STATE 4-22 (API #005-06602
EngineerForm: (02 )
401131578
4/4/2017
Bradenhead tests shall be performed and reported according to the following schedule and Form 17 submitted within 10 days of each test: 1) Within 60 days of rig release, prior to stimulation. 2) 6 months after rig release, prior to stimulation. 3) Within 30 days of first production, as reported on Form 5A.
EngineerForm: (02 )
401131578
4/4/2017
1) Submit Form 42 electronically to COGCC 48 hours prior to MIRU for the first well activity with a rig on the pad and provide 48 hour spud notice via Form 42 for all subsequent wells drilled on the pad. 2) Comply with Rule 317.j. and provide cement coverage from TD to a minimum of 200' above Niobrara. Verify coverage with cement bond log.
EngineerForm: (04 )
401438082
4/11/2018
Gas analysis for well including H2S should be submitted via Sundry Notice, Form 4 and EDD by May 15, 2018.
EngineerForm: (04 )
401438082
4/11/2018
1) Flaring of natural gas shall comply with COGCC Rule 912. 2) Submit requests to flare annually to COGCC on Form 4 (Sundry Notice), which discusses timing to connect to sales line, plans to develop infrastructure, and justification for continued venting/flaring. Provide gas analysis including H2S with each Sundry Notice. 3) Report metered flaring volumes on Form 7, Operator’s Monthly Report of Operations. 4) The operator is required to obtain and maintain any required air permits from CDPHE. 5) The expectation for permanent flares controlling separators will be an enclosed combustion device with a 98% design destruction efficiency for hydrocarbons. No open flares. 6) Notify the local emergency dispatch or the local governmental designee of natural gas flaring.
EngineerForm: (04 )
401438082
4/11/2018
This approval is good for one year and new application must be made before October 1, 2018.
EngineerForm: (04 )
401438082
4/11/2018
This approval for flaring is for the applied-for well and not to be construed that approval will be given for additional wells developed on this pad or additional pads.
EngineerForm: (04 )
402574624
2/24/2022
All tank vapors should be appropriately controlled (combusted).
 
COGIS - Best Management Practice Results
BMP TypeSource DocumentBest Management Practices
Drilling/Completion OperationsForm: (02 )
401131578
4/6/2017
Alternative Logging Program - Multi-Well Pad: One of the first wells drilled on the pad will be logged with open-hole Resistivity Log and Gamma Ray Log from the kick-off point into the surface casing. All wells on the pad will have a cement bond log with gamma-ray run on production casing (or on intermediate casing if production liner is run) into the surface casing. The horizontal portion of every well will be logged with a measured-while-drilling gamma-ray log. The Form 5, Completion Report, for each well on the pad will list all logs run and have those logs attached. The Form 5 for a well without open-hole logs shall clearly state “No open-hole logs were run” and shall clearly identify (by API#, well name & number) the well in which open-hole logs were run.