Engineer | Form: (02 ) 400839652 12/16/2015 | Operator acknowledges the proximity of the listed wells. Operator agrees to: provide mitigation option 1 or 2 (per the DJ Basin Horizontal Offset Policy) to mitigate the situation, ensure all applicable documentation is submitted based on the selected mitigation option chosen, and submit a Form 42 (“OFFSET MITIGATION COMPLETED”) stating that appropriate mitigation occurred and that it has been completed, prior to the hydraulic stimulation of this well.
Newlander H Unit 1 (05-001-09192)
Rule 12-35 (05-123-20746)
Weigandt 43-3 (05-001-09095) |
Engineer | Form: (02 ) 400839652 12/16/2015 | 1) Submit Form 42 electronically to COGCC 48 hours prior to MIRU for the first well activity with a rig on the pad and provide 48 hour spud notice via Form 42 for all subsequent wells drilled on the pad.
2) Comply with Rule 317.j. and provide cement coverage from TD to a minimum of 200' above Niobrara and from 200’ below Sussex to 200’ above Sussex. Verify coverage with cement bond log. |
Engineer | Form: (04 ) 401091089 8/11/2016 | 1) Submit Form 42 electronically to COGCC 48 hours prior to MIRU (spud notice) for the first well activity with a rig on the pad and provide 48 hour spud notice via Form 42 for all subsequent wells drilled on the pad.
2) Comply with Rule 317.j. and provide cement coverage from TD to a minimum of 200' above Niobrara and from 200’ below Sussex to 200’ above Sussex. Verify coverage with cement bond log.
|
Engineer | Form: (04 ) 401091089 8/11/2016 | Bradenhead tests shall be performed and reported according to the following schedule and Form 17 submitted within 10 days of each test.
1) Within 60 days of rig release, prior to stimulation.
2) 6 months after rig release, prior to stimulation.
3) Within 30 days of first production, as reported on Form 5A. |
Engineer | Form: (04 ) 401091089 8/11/2016 | Operator acknowledges the proximity of the listed wells. Operator agrees to: provide mitigation option 1 or 2 (per the DJ Basin Horizontal Offset Policy) to mitigate the situation, ensure all applicable documentation is submitted based on the selected mitigation option chosen, and submit a Form 42 (“OFFSET MITIGATION COMPLETED”) stating that appropriate mitigation occurred and that it has been completed, prior to the hydraulic stimulation of this well.
Newlander H Unit 1 (05-001-09192)
Rule 12-35 (05-123-20746)
Weigandt 43-3 (05-001-09095) |
Engineer | Form: (04 ) 401105343 9/8/2016 | This Form 4 makes changes to the approved Form 2 and must be displayed with the Form 2 while drilling. Changes a COA for mitigation from Option 1 or 2 to Option 4.
Operator acknowledges the proximity of the listed well. Operator assures that this offset will be remediated per the DJ Basin Horizontal Offset Policy (option 4). Operator will submit a Form 42 (“OTHER – AS SPECIFIED BY PERMIT CONDITION”) stating that appropriate mitigation will be completed, during the hydraulic stimulation of this well. This Form 42 shall be filed 48 hours prior to stimulation. A Bradenhead test will be performed prior to the beginning of stimulation and the Form 17 submitted within 10 days. Surface and production casing pressures will be actively monitored during stimulation. Operator will assure that the offset well’s Bradenhead is open and monitored during the entire stimulation treatment – a person will monitor for any evidence of fluid. If there is indication of communication between the stimulation treatment and the offset well, treatment will be stopped and COGCC Engineering notified.
Newlander H. Unit 1, API 05-001-09192 |