Engineer | Form: (02 ) 2590834 11/19/2010 | 1) Note surface casing setting depth change from 900’ to 980’. Increase cement coverage accordingly and cement to surface.
2) Provide 24 hour notice of MIRU to Jim Precup at 303-469-1902 or e-mail at james.precup@state.co.us
3) Comply with Rule 317.i and provide cement coverage from TD to a minimum of 200' above Niobrara and from 200’ below Shannon to 200’ above Sussex. Verify coverage with cement bond log.
4) Comply with Rule 321. Run and submit Directional Survey from TD to base of surface casing. Ensure that the wellbore complies with setback requirements in commission orders or rules prior to producing the well.
|
Engineer | Form: (06 ) 401874807 4/12/2019 | Plugging
• Provide 48 hour notice of plugging MIRU via electronic Form 42.
• Plugs and squeezes will be placed as stated in the plugging procedure of the approved NOI unless revised by COA or prior approval from COGCC is obtained.
• COGCC Change: Move casing cut to 2500’, open hole plug to 2500-2300’, below base of UPA.
• Tag 2500-2300’ plug if circulation is not maintained during pumping and displacement of plug to depth, 100’ minimum height required.
• Due to a history of Bradenhead pressure as reported on the pre-plugging Form 17 operator will wait 8 hours after pumping plug at 2500-2300’, tag and assure that there is no pressure or flow before proceeding with plugging operations. Contact COGCC Area Engineer if well is not static at this time.
• COGCC Change: Increase surface plug to 100-0’, adjust cement volume accordingly, aquifer.
• Check for fluid migration or shut-in pressure on the well prior to pumping any plug(open hole, annular or casing) that isolates deepest aquifer or the surface casing shoe (whichever is deeper). Contact COGCC Engineer for revised plugging orders if well is not static at this time, prior to continuing with plugging operations.
• Tag required if the shoe plug, or combined stub/shoe plug, is not circulated to the surface. Shoe plug shall be placed as specified herein and the top of cement must be a minimum 50’ into the shoe, or 50’ above the stub (if not cut below the shoe), whichever is shallower.
• Place a 50' plug (minimum) at the surface, both inside the inner most casing and in all annular spaces. All other cement plugs, without mechanical isolation, shall have at least 100' of cement left in the casing.
• Properly abandon on-location flowlines as per Rule 1105. File electronic Form 42 once abandonment complete. Within 30 days of an operator completing abandonment requirements for an off-location flowline or crude oil transfer line the operator must submit a Flowline Report, Form 44.
• Document all COAs have been satisfied on Form 6 SRA.
|
Engineer | Form: (06 ) 401874807 4/12/2019 | Bradenhead Testing
• Prior to the start of plugging operations, a bradenhead test shall be performed and reported if there has not been a reported bradenhead test within the 60 days immediately preceding the start of plugging operations.
• If any of the following conditions exist then sampling of all fluids is required and sampling methods shall comply with Operator Guidance – Bradenhead Testing and Reporting Instructions, Appendix A: Liquid and Gas Sampling as found on the COGCC website, cogcc.state.co.us.
1) The initial pressure measurement on the bradenhead is greater than 25 psi, prior to blowing down any liquid or gas from the bradenhead valve, or
2) Pressure remains at the conclusion of the test, or
3) Any liquids are present anytime during the test. If so, then stop the test as soon as liquids are present and sample before resuming the test.
• Form 17 Bradenhead Test Report shall be submitted within 10 days of the test.
• If samples are collected, copies of all final laboratory analytical results shall be provided to the COGCC within three (3) months of collecting the samples. Submit via a Form 43 to upload the laboratory results to the COGCC Environmental Database. Form 43 instructions are on COGCC’s website under Regulation => Forms => Form 43 COGCC Environmental Database.
|
Engineer | Form: (06 ) 401874807 4/12/2019 | Venting
Operator shall implement measures to control unnecessary and excessive venting, to protect the health and safety of the public, and to ensure that vapors and odors from well plugging operations do not constitute a nuisance or hazard to public welfare.
|
Engineer | Form: (06 ) 402431528 7/16/2020 | Plugging
1) Provide 48 hour notice of plugging MIRU via electronic Form 42.
2) Properly abandon flowlines as per Rule 1105. File electronic Form 42 once abandonment complete. Within 30 days of an operator completing abandonment requirements for an off-location flowline or crude oil transfer line the operator must submit a Flowline Report, Form 44.
3) Plugs and squeezes will be placed as stated in the Plugging Procedure section of the approved NOIA unless revised by COA or prior approval from COGCC is obtained.
4) The wellbore must be static prior to placing cement plugs which are to be a minimum of 100' in length for all but surface plugs. Mechanical isolation requires a 25' cement plug, minimum.
5) Place a 50' plug (minimum) at the surface, both inside the inner most casing and in all annular spaces. Surface plugs shall be circulated to surface. Confirm cement to surface in all strings during cut and cap.
6) With the Form 6 SRA operator must provide written documentation which positively affirms each COA has been addressed.
7) Contact COGCC Area Inspector prior to commencing plugging operations.
8) After placing the shallowest hydrocarbon isolating plug (7737'), operator must wait a sufficient time on all subsequent plugs to confirm static conditions. If at any time after placing this plug there is evidence of pressure or of fluid migration, contact COGCC Area Engineer before continuing operations.
9) Pump 20 sx plug from 4870-4670'. Tag required if circulation is not maintained while pumping plug and displacing to depth.
10) Add 50 sx squeeze at 3550'. Leave 100' of cement in the csg if a CICR is not used.
11) Due to a history of bradenhead pressure as reported on the pre-plugging Form 17, wait 8 hours after pumping plug/squeeze at 3550’, in order to assure that there is no pressure or flow before proceeding with plugging operations. Contact COGCC Area Engineer if well is not static at this time.
12) Assure that wellbore is static prior to pumping 125 sx shoe plug from 1055-680', tag.
13) Suface plug shall be continous from top of shoe plug at 680' to surface. Tag required if cement does not circulate to surface prior to pumping additonal cement. |
Engineer | Form: (06 ) 402431528 7/16/2020 | Bradenhead Testing
Prior to starting plugging operations a bradenhead test shall be performed if there has not been a reported bradenhead test within the 60 days immediately preceding the start of plugging operations.
1) If, before opening the bradenhead valve, the beginning pressure is greater than 25 psi, sampling is required.
2) If pressure remains at the conclusion of the test, or if any liquids were present during the test, sampling is required.
The Form 17 shall be submitted within 10 days of the test. Sampling shall comply with Operator Guidance - Bradenhead Testing and Reporting Instructions. If samples are collected, copies of all final laboratory analytical results shall be provided to the COGCC within three (3) months of collecting the samples.
If there is a need for sampling, contact COGCC engineering for verification of plugging procedure. |
Engineer | Form: (06 ) 402431528 7/16/2020 | Venting
Operator shall implement measures to control unnecessary and excessive venting, to protect the health and safety of the public, and to ensure that vapors and odors from well plugging operations do not constitute a nuisance or hazard to public welfare. |