| Agency | Form: (02) 2586151 07/21/2010 | 1) Provide 24 hour notice of MIRU to Jim Precup at 303-469-1902 or e-mail at james.precup@state.co.us
2) Comply with Rule 317.i and provide cement coverage from TD to a minimum of 200' above Niobrara and from 200’ below Shannon to 200’ above Sussex. Verify coverage with cement bond log.
3) Comply with Rule 321. Run and submit Directional Survey from TD to base of surface casing. Ensure that the wellbore complies with setback requirements in commission orders or rules prior to producing the well.
|
| OGLA | Form: (06) 403159471 09/15/2022 | Due to close proximity to Residential Building Units: prior to commencing operations, at a minimum, the operator will provide an informational sheet to the owners/occupants of BUs that are nearby and adjacent to the parcel on which the well is located. The sheet will include the operator's contact information and the nature, timing, and expected duration of the P&A operations. |
| OGLA | Form: (06) 403159471 09/15/2022 | This oil and gas location is within 0.5-mile of a CPW-mapped bald eagle nest site buffer and bald eagle roost site Rule 309.e.(1) consultation habitat. CPW may choose to consult on this planned P&A to develop site specific measures to avoid, minimize, and mitigate impacts to wildlife prior to conducting the work. Please note that non-emergency plugging and abandonment (P&A) activities should not take place from November 15 to July 31. Please confirm via email if a consultation with CPW has or will occur and provide any operator BMPs that are the result of that consultation. |
| OGLA | Form: (06) 403159471 09/15/2022 | Due to proximity to a wetland, surface water and expected shallow groundwater, operator will use secondary containment for all tanks and other liquid containers. Operator will implement stormwater BMPs and erosion control measures as needed to prevent sediment and stormwater runoff from entering the wetland and surface water. |
| Engineer | Form: (06) 403159471 09/26/2022 | Prior to starting plugging operations a bradenhead test shall be performed if there has not been a reported bradenhead test within the 60 days immediately preceding the start of plugging operations.
1) If, before opening the bradenhead valve, the beginning pressure is greater than 25 psi, sampling is required.
2) If pressure remains at the conclusion of the test, or if any liquids were present during the test, sampling is required.
The Form 17 shall be submitted within 10 days of the test. Sampling shall comply with Operator Guidance - Bradenhead Testing and Reporting Instructions. If samples are collected, copies of all final laboratory analytical results shall be provided to the COGCC within three (3) months of collecting the samples.
If there is a need for sampling, contact COGCC engineering for verification of plugging procedure.
|
| Engineer | Form: (06) 403159471 09/26/2022 | 1) Provide electronic Form 42 Notice of MIRU 2 business days ahead of operations and electronic Form 42 Notice of Plugging Operations 48 hours prior to mobilizing for plugging operations. These are two separate notifications, required by Rules 405.e and 405.l.
2) After placing plug at 2300’ assure that all fluid migration has been eliminated by monitoring the well for a minimum of 8 hours before proceeding to the next plug. If at any time after placing this plug there is evidence of pressure or of fluid migration, contact COGCC engineering before continuing operations.
3) Prior to placing cement above the base of the Upper Pierre: verify that all fluid (liquid and gas) migration has been eliminated. If evidence of fluid migration or pressure remains, contact COGCC Engineer for an update to plugging orders.
4) If surface casing shoe plug cement is not circulated to surface, shut-in, WOC 4 hours then tag plug – must be at 728’ or shallower and provide a minimum of 10 sx plug at the surface.
5) Leave at least 100’ of cement in the wellbore for each plug without mechanical isolation.
6) With the Form 6 SRA operator must provide written documentation which positively affirms each COA listed above has been addressed.
|
| Engineer | Form: (06) 403159471 09/26/2022 | Consistent with Rule 911.a, a Form 27 must be approved prior to cut and cap, conducting flowline abandonment, or removing production equipment. Allow 30 days for Director review of the Form 27; include the Form 27 document number on the Form 44 for offsite flowline abandonment (if applicable) and on the Form 6 Subsequent.
Properly abandon flowlines per Rule 1105. If flowlines will be abandoned in place, include with the Form 27: pressure test results conducted in the prior 12 months as well as identification of any document numbers for a COGCC Spill/Release Report, Form 19, associated with the abandoned line.
|
| Engineer | Form: (04) 403181187 10/14/2022 | 1. Operator will implement measures to control venting, to protect health and safety, and to ensure that vapors and odors from well operations do not constitute a nuisance or hazard to public welfare.
2. Well to be repaired / plugged by 09/30/2023. Summary of well monitoring and mitigation to be submitted on a Form 4 Sundry after well has been repaired / plugged and abandoned. The sundry should include pressure data, flow rate information, sample analysis interpretation, and bradenhead test description.
3. Shut in bradenhead pressure shall not exceed 50 psig.
4. If a sample has not been collected within the last twelve months collect bradenhead and production gas samples for laboratory analysis. Sampling will comply with Operator Guidance - Bradenhead Testing and Reporting Instructions, Appendix A: Liquid and Gas Sampling. Copies of all final laboratory analytical results will be provided to the COGCC within three months of collecting the samples. |
| Engineer | Form: (04) 403223129 11/21/2022 | 1. Operator will implement measures to control venting, to protect health and safety, and to ensure that vapors and odors from well operations do not constitute a nuisance or hazard to public welfare.
2. Well to be plugged by 09/30/2023. Summary of well monitoring and mitigation to be submitted on a Form 4 Sundry after well has been plugged and abandoned. The sundry should include pressure data, flow rate information, sample analysis interpretation, and bradenhead test description.
3. Shut in bradenhead pressure shall not exceed 50 psig.
4. If a sample has not been collected within the last twelve months collect bradenhead and production gas samples for laboratory analysis. Sampling will comply with Operator Guidance - Bradenhead Testing and Reporting Instructions, Appendix A: Liquid and Gas Sampling. Copies of all final laboratory analytical results will be provided to the COGCC within three months of collecting the samples.
|