Agency | Form: (02 ) 400007434 1/25/2010 | COGCC ENG COA - SME Note surface casing setting depth change from 700’ to 740’. Increase cement coverage accordingly and cement to surface. 1) Provide 24 hr notice of spud to Ed Binkley at 970-506-9834 or e-mail at ed.binkley@state.co.us . 2) Set surface casing per Rule 317d, cement to surface. Setting surface casing less than the approved depth is a permit violation unless prior written approval is obtained from the COGCC. 3) If completed, provide cement coverage from TD to a minimum of 200' above Niobrara and from 200’ below to 200’ above Sussex. Verify coverage with cement bond log. 4) Comply with Rule 321. Run and submit Directional Survey from TD to base of surface casing. Ensure that the wellbore complies with setback requirements in commission orders or rules prior to producing the well.
|
Agency | Form: (02 ) 400007434 2/9/2010 | COGCC ENG COA - SME Note surface casing setting depth change from 700’ to 740’. Increase cement coverage accordingly and cement to surface. 1) Provide 24 hr notice of spud to Ed Binkley at 970-506-9834 or e-mail at ed.binkley@state.co.us . 2) Set surface casing per Rule 317d, cement to surface. Setting surface casing less than the approved depth is a permit violation unless prior written approval is obtained from the COGCC. 3) If completed, provide cement coverage from TD to a minimum of 200' above Niobrara and from 200’ below to 200’ above Sussex. Verify coverage with cement bond log. 4) Comply with Rule 321. Run and submit Directional Survey from TD to base of surface casing. Ensure that the wellbore complies with setback requirements in commission orders or rules prior to producing the well.
|
Engineer | Form: (04 ) 402704572 2/8/2022 | This approval is good for one year and a new application must be made before June 1, 2022. Updates for the planned utilization of the well should be included with the application.
|
Engineer | Form: (04 ) 402704572 2/8/2022 | The Form 7 reporting must reflect the well status dates reported on the Form 4-TA request.
|
Engineer | Form: (04 ) 403003071 6/16/2022 | 1) This well is designated inactive and must be properly returned to production, plugged and abandoned, have an approved Form 5B or be submitted on a Form 6A (to be designated as Out of Service) no later than no later than November 1, 2022. |
OGLA | Form: (06 ) 403452518 7/7/2023 | Notification will be given to any adjacent building unit occupants within a 1000 feet of the wellhead of planned P&A start date. |
OGLA | Form: (06 ) 403452518 7/7/2023 | 3rd party wildlife surveys will be conducted on this well prior to rigging up for P&A activities. Should sensitive HPH conditions be identified during the screening process, Chevron will delay the work until conditions (nesting) clear and/or consult directly with CPW for guidance and discussion of potential mitigation measures that may be incorporated. |
Permit | Form: (06 ) 403452518 7/11/2023 | Submit Operator's Monthly Production Reports (Form 7) required for compliance with Rule 413 within 30 days. Missing 9/2013. |
Engineer | Form: (06 ) 403452518 7/18/2023 | Prior to starting plugging operations a bradenhead test shall be performed if there has not been a reported bradenhead test within the 60 days immediately preceding the start of plugging operations.
1) If, before opening the bradenhead valve, the beginning pressure is greater than 25 psi, sampling is required.
2) If pressure remains at the conclusion of the test, or if any liquids were present during the test, sampling is required.
The Form 17 shall be submitted within 10 days of the test. Sampling shall comply with Operator Guidance - Bradenhead Testing and Reporting Instructions. If samples are collected, copies of all final laboratory analytical results shall be provided to the ECMC within three (3) months of collecting the samples.
If there is a need for sampling, contact ECMC engineering for verification of plugging procedure.
|
Engineer | Form: (06 ) 403452518 7/18/2023 | 1) Provide electronic Form 42 Notice of MIRU 2 business days ahead of operations and electronic Form 42 Notice of Plugging Operations 48 hours prior to mobilizing for plugging operations. These are two separate notifications, required by Rules 405.e and 405.l.
2) Prior to placing cement above the base of the Upper Pierre (approximately 1710’) : verify that all fluid (liquid and gas) migration has been eliminated. If evidence of fluid migration or pressure remains, contact ECMC Engineer for an update to plugging orders.
3) Pump surface casing shoe plug only after isolation has been verified. Circulate cement to surface if production casing is not pulled.
4) Leave at least 100’ of cement in the wellbore for each plug without mechanical isolation.
5) With the Form 6 SRA operator must provide written documentation which positively affirms each COA listed above has been addressed.
|
Engineer | Form: (06 ) 403452518 7/18/2023 | Consistent with Rule 911.a, a Form 27 must be approved prior to cut and cap, conducting flowline abandonment, or removing production equipment. Allow 30 days for Director review of the Form 27; include the Form 27 document number on the Form 44 for offsite flowline abandonment (if applicable) and on the Form 6 Subsequent.
Properly abandon flowlines per Rule 1105. If flowlines will be abandoned in place, include with the Form 27: pressure test results conducted in the prior 12 months as well as identification of any document numbers for a ECMC Spill/Release Report, Form 19, associated with the abandoned line.
|