Skip to Main Content

COGIS DB

 
Facility TypeFacility ID/
API
Facility Name/
Number
Operator Name/
Number
StatusField Name/
Number
LocationLocation IDRelated Facilities
WELL05-123-15093EISENACH & PRESTON
8-8K
KERR MCGEE OIL & GAS ONSHORE LP
47120
PA
11/24/2025
WATTENBERG
90750
WELD  123
SENE 8 3N66W 6
327738View Related
 
COGIS - Conditions of Approval Results
TypeSource DocumentConditions of Approval
EngineerForm: (06)
401870502
03/11/2019
Operator shall implement measures to control venting, to protect health and safety, and to ensure that vapors and odors from well plugging operations do not constitute a nuisance or hazard to public welfare.
EngineerForm: (06)
401870502
03/11/2019
1) Provide 48 hour notice of plugging MIRU via electronic Form 42. 2) Prior to placing the 1,165' plug: verify that all fluid migration (liquid or gas) has been eliminated. If evidence of fluid migration or pressure remains, contact COGCC Engineer for an update to plugging orders. 3) After isolation has been verified, pump plug and displace. If cement is not circulated to surface, shut-in, WOC 4 hours then tag plug – must be at 459' or shallower and provide 10 sack plug at surface. 4) Leave at least 100’ of cement in the wellbore for each plug. 5) Properly abandon on-location flowlines as per Rule 1105. File electronic Form 42 once abandonment is complete. Within 30 days of an operator completing abandonment requirements for an off-location flowline or crude oil transfer line, the operator must submit a Flowline Report, Form 44.
EngineerForm: (06)
401870502
03/11/2019
If there has not been a reported Bradenhead test within 60 days of plugging this well, prior to starting plugging operations, a Bradenhead test shall be performed. 1) If, before opening the Bradenhead valve, the beginning pressure is greater than 25 psi, sampling is required. 2) If pressure remains at the conclusion of the test, or if any liquids were present during the test, sampling is required. 3) If sampling is required contact COGCC engineering for a confirmation of plugging requirements prior to placing any plugs. Sampling shall comply with Operator Guidance - Bradenhead Testing and Reporting Instructions. The Form 17 shall be submitted within 10 days of the test.
EngineerForm: (06)
401870502
03/11/2019
Operator to submit Gyro survey dated 07/17/2013 as indicated on the submitted plugging procedure with the Form SROA.
EngineerForm: (04)
404176643
04/23/2025
1) Provide electronic Form 42 Notice of MIRU 2 business days ahead of operations. 2) Operator shall implement measures to control venting, to protect health and safety, and to ensure that vapors and odors from well operations do not constitute a nuisance or hazard to public welfare. 3) Form 4, Sundry Notice for temporarily abandoned status required for all wells incapable of production. Submit a Form 4 TA Sundry within 30 days of temporarily abandoning the well 4) A Form 5A, Completed Interval Report, is required to report all plugs downhole which isolate any perforated interval. Submit a Form 5A within 30 days of temporarily abandoning the well.
EngineerForm: (06)
404306399
08/12/2025
1) Provide electronic Form 42 Notice of MIRU 2 business days ahead of operations and electronic Form 42 Notice of Plugging Operations 48 hours prior to mobilizing for plugging operations. These are two separate notifications, required by Rules 405.e and 405.l. 2) Prior to placing cement above the base of the Upper Pierre (1485') : verify that all fluid (liquid and gas) migration has been eliminated. If evidence of fluid migration or pressure remains, contact ECMC Engineer for an update to plugging orders. 3) Pump surface casing shoe plug at 1400' only after isolation has been verified. If surface casing cement is not circulated to surface, shut-in, WOC 4 hours then tag plug – must be at 459' or shallower and provide a minimum of 10 sx plug at the surface. 4) Leave at least 100’ of cement in the wellbore for each plug without mechanical isolation. 5) After cut and prior to cap, verify isolation by either a 15 minute bubble test or 15 minute optical gas imaging recording. If there is indication of flow contact ECMC Engineering. Provide a statement on the 6SRA which method was used and what was observed. Retain records of final isolation test for 5 years. 6) With the Form 6 SRA operator must provide written documentation which positively affirms each COA listed above has been addressed.
EngineerForm: (06)
404306399
08/12/2025
Consistent with Rule 911.a, a Form 27 must be approved prior to cut and cap, conducting flowline abandonment, or removing production equipment. Allow 30 days for Director review of the Form 27; include the Form 27 document number on the Form 44 for offsite flowline abandonment (if applicable) and on the Form 6 Subsequent. Properly abandon flowlines per Rule 1105. If flowlines will be abandoned in place, include with the Form 27: pressure test results conducted in the prior 12 months as well as identification of any document numbers for a ECMC Spill/Release Report, Form 19, associated with the abandoned line.
EngineerForm: (06)
404306399
08/12/2025
Prior to starting plugging operations a bradenhead test shall be performed if there has not been a reported bradenhead test within the 60 days immediately preceding the start of plugging operations. 1) If, before opening the bradenhead valve, the beginning pressure is greater than 25 psi, sampling is required. 2) If pressure remains at the conclusion of the test, or if any liquids were present during the test, sampling is required. The Form 17 shall be submitted within 10 days of the test. Sampling shall comply with Operator Guidance - Bradenhead Testing and Reporting Instructions. If samples are collected, copies of all final laboratory analytical results shall be provided to the ECMC within three (3) months of collecting the samples. If there is a need for sampling, contact ECMC engineering for verification of plugging procedure.
EngineerForm: (06)
404306399
08/12/2025
WITH KNOWN BRADENHEAD PRESSURE After placing plug at 2100' assure that all fluid migration has been eliminated by monitoring the well for a minimum of 8 hours before proceeding to the next plug. If at any time after placing this plug there is evidence of pressure or of fluid migration, contact ECMC engineering before continuing operations.
OGLAForm: (06)
404306399
08/20/2025
COA's provided by the operator as Best Management Practices under Technical Detail / Comments: Signage for P&As: Prior to commencing operations, Kerr McGee will post signs in conspicuous locations.  The signs will indicate plugging and abandonment operations are being conducted, the well name, well, and the Operator’s contact information.  Signs will be placed so as not to create a potential traffic hazard. Notifications: Courtesy notifications will be sent to all parcel owners with building units within 1,500 feet of the location letting them know about out plugging and abandonment operations and providing contact information for Kerr McGee's response line and online resources. Wellbore Pressure: In some cases, wellbore pressure drawdown operations may occur approximately 1-2 days prior to Move In Rig Up (MIRU) of the workover rig. This is conducted to allow for reduced time that the workover rig is needed on location. These operations will be conducted in accordance with Form 4 and/or Form 6 requirements. Water: Water will be placed on dirt access roads to mitigate dust as needed. Lighting: Operations are daylight-only; no lighting impacts are anticipated from operations. Noise: Operations will be in compliance with Table 423-1 requirements. Based off the rig sound signature, rig orientation will be considered to reduce noise levels to nearby building units. Environmental Concerns: This location was reviewed using a desktop method to review publicly available wildlife data (including CPW & ECMC data) as well as internal wildlife datasets and aerial imagery. All field personnel are trained to identify wildlife risks and raise concerns noticed during operations with the KMOG Health, Safety, and Environment (HSE) department.
OGLAForm: (06)
404306399
08/20/2025
Due to proximity to a wetland and surface water, operator will use secondary containment for all tanks and other liquid containers. Operator will implement stormwater BMPs and erosion control measures as needed to prevent sediment and stormwater runoff from entering the wetland and surface water.
EngineerForm: (06)
404306399
08/20/2025
Operator shall implement measures to control venting, to protect health and safety, and to ensure that vapors and odors from well plugging operations do not constitute a nuisance or hazard to public welfare.
 
COGIS - Best Management Practice Results
BMP TypeSource DocumentBest Management Practices
PlanningForm: (04 )
404176643
4/23/2025
Site lighting will be shielded and directed downward and inward toward operations to avoid glare on public roads and nearby Building Units.
Community Outreach and NotificationForm: (04 )
404176643
4/23/2025
Signs will be placed in conspicuous locations and will include Oxy contact information; the Oxy Stakeholder Relations team will respond to all community member inquiries. The signs will be placed so as not to create a potential traffic hazard.
Community Outreach and NotificationForm: (04 )
404176643
4/23/2025
Courtesy notifications will be sent to all parcel owners with building units within 2,000 feet of the location letting them know about our subsequent well operations and providing contact information for Kerr McGee’s response line and online resources.
WildlifeForm: (04 )
404176643
4/23/2025
This location was reviewed using a desktop method to review publicly available wildlife data (including CPW & ECMC data) as well as internal wildlife datasets and aerial imagery. All field personnel are trained to identify wildlife risks and raise concerns noticed during operations with the Kerr McGee's Health, Safety, and Environment (HSE) department.
Dust controlForm: (04 )
404176643
4/23/2025
Water will be placed on dirt access roads to mitigate dust as needed
Noise mitigationForm: (04 )
404176643
4/23/2025
Noise associated with pipe handling, traffic, and other operational activity will be minimized between 7:00 pm and 7:00 am. Based off the rig sound signature, rig orientation will be considered to reduce noise levels to nearby building units.