| Engineer | Form: (06) 400603516 05/08/2014 | 1) Submit Form 42 electronically to COGCC 48 hours prior to MIRU.
2) No CBL on file. Run CBL to verify the top of primary cement is at least 200’ over Niobrara, at least 50’ below Sussex to 50’ above Sussex, and adequately isolates the Fox Hills aquifer. If cement does not exist as required, provide this coverage as part of this plugging project.
3) For 1530' plug: pump plug and displace, shut-in, WOC 4 hours and tag plug – must be 527’ or shallower.
4) Properly abandon flowlines as per Rule 1103. File electronic Form 42 once abandonment complete. |