Engineer | Form: (06 ) 401304933 7/11/2017 | 1) Prior to starting plugging operations a bradenhead test shall be performed. If the beginning pressure is greater than 25 psi, or if pressure remains at the conclusion of the test, or if any liquids were present contact COGCC Engineer for sampling requirements. The Form 17 shall be submitted within 10 days of the test.
2) Provide 48 hour notice of plugging MIRU via electronic Form 42.
3) Properly abandon flowlines as per Rule 1103. File electronic Form 42 once abandonment complete.
4) No CBL on file with COGCC. Verify existing cement with a CBL prior to plugging and submit CBL with Form 6 Subsequent Report of Abandonment. If cement is not present on CBL as outlined on this Form contact COGCC engineer for an update to plugging orders.
5) Production casing stub plug is also surface casing shoe plug, if this plug is not circulated to surface then tag plug – must be 492’ or shallower and provide a 15 sack plug at the surface. Leave at least 100’ cement in the wellbore for each plug. |