| Agency | Form: (02) 2582215 05/19/2010 | 1) Provide 24 hour notice of MIRU to Jim Precup at 303-469-1902 or e-mail at james.precup@state.co.us
2) Per 3/4/96 CBL on file TOC is 6970’ (Niobrara top is 6940’). Provide remedial cement from 6970’-6740’ (200’ above Niobrara). Verify w/ CBL.
3) Run and/or submit CBL to verify stage cement coverage stated as 673’-430’. Provide remedial cement from 870’ to existing BOC or 50’ above surface casing shoe if stage cement is not present. Verify with CBL. |
| Permit | Form: (06) 401049562 05/23/2016 | The JSand was TA'd with a sand plug @ 7100' back in 6/2/2010. Refile form 7 to reflect the JSand TA. |
| Engineer | Form: (06) 401049562 05/24/2016 | 1) Provide 48 hour notice of plugging MIRU via electronic Form 42.
2) Properly abandon flowlines as per Rule 1103. File electronic Form 42 once abandonment complete.
3) Please submit gyro survey data with Form 6 (s) Subsequent Report of Abandonment.
4) Leave at least 100’ of cement in the wellbore for each plug.
|