UIC | Form: (04 ) 401318656 6/26/2017 | All repairs of the Union Pacific 56-21 must be completed or the well plugged and abandoned by December 3, 2017. Injection may not resume until the well is repaired and it passes an Mechanical Integrity Test witnessed by COGCC staff.
|
UIC | Form: (05A ) 401320420 6/28/2017 | Casing failed to blow down during UIC Field Inspection on June 1, 2017 (FIR Doc # 680401605, 6/3/2017). Chevron has 6 months to repair or plug and abandon the well. Work must be completed before December 3, 2017. Note: The Field Inspection Report Corrective Action date was set at 3 months not 6 months. Sundry Doc # 401318656 granted an extension 6 months for repair or plugging before December 3, 2017. |
UIC | Form: (04 ) 401398177 9/14/2017 | Well must pass a Mechanical Integrity Test witnessed by COGCC prior to resuming injection. Operator may receive verbal permission to inject from field inspector but must file Form 21 for MIT within 30 days. |
UIC | Form: (04 ) 402177832 9/19/2019 | File Form 5 to report casing repair and cement work. |
Engineer | Form: (04 ) 402269632 11/10/2020 | 1) This approval is good for one year and a new application must be made before 03/31/2021 (1 year from prior application). Updates for the planned utilization of the well should be included with the application.
2) The Form 7 reporting must reflect the well status dates reported on the Form 4-TA request.
3) A Form 5A is required to report all plugs currently downhole which isolate the perforated interval.
|