Engineer | Form: (05 ) 2555969 2/11/2011 | opr provided form 5A: well to be converted to UIC. pulled PR eqpt; clean out wellbore; ran new tubing... see doc # 1905692 (Form 4) for 'change-over' procedure |
Engineer | Form: (04 ) 403895886 8/28/2024 | 1) For applicable operations, submit a Form 5 or 5A (updated packer and tubing depths) within 30 days of the work with job related documents including a minimum of one of the following attachments: operations summary, cement job summary and/or wireline summary. Additionally, include CBL’s and any additional logs run.
2) Complete a Form 21 MIT to verify repairs for injection wells
|