| Engineer | Form: (02) 401227323 07/18/2017 | 1) Provide 48 hour notice prior to spud via electronic Form 42.
2) Set at least 420’ of surface casing.
3) If production casing is set provide cement coverage to at least 200’ above the shallowest completed interval or Spergen, whichever is shallower and across Cheyenne/Dakota interval (5200’ to 4600’ min). Run and submit CBL to verify cemented intervals.
4) If well is a dry hole set plugs at the following depths: 40 sks cement +/- 50’ above the Spergen, 40 sks cement across any DST w/ show, 40 sks cement 50’ below Cheyenne (5200’), 40 sks cement 50’ above top of Dakota (4600’), 50 sks cement from 50’ below surface casing shoe up into surface casing, 15 sks cement in top of surface casing, cut 4 ft below GL, weld on plate, 5 sks cement each in rat hole and mouse hole. |
| Engineer | Form: (02) 401227323 07/18/2017 | Bradenhead tests shall be performed and reported according to the following schedule
and Form 17 submitted within 10 days of each test.:
1) All: Within 60 days of rig release, prior to stimulation.
2) Delayed completion: 6 months after rig release, prior to stimulation.
3) All: Within 30 days of first production, as reported on Form 5A.
|
| Agency | Form: (02) 401852443 12/27/2018 | 1) Provide 48 hour notice prior to spud vai electronic Form 42.
2) Set at least 440' of surface casing (5% of proposed TVD). Cement to surface.
3) If production casing is set provide cement coverage to at least 200' above the shallowest completed interval or Lansing, whichever is shallower and across Cheyenne/Dakota interval (5200' to 4600' min). Run and submit CBL to verify cemented intervals.
4) If well is a dry hole, set plugs at the following depths: 40 sks cement +/- 50' above the Spergen, 40 sks cement +/- above the Lansing, 40 sks cement across any DST w/ show, 40 sks cement 100' below Cheyenne (5200'), 40 sks cement 50' above top of Dakota (4600'), 50 sks cement from 50' below surface casing show up into surface casing. 15 sks cement in top of surface casing, cut 4 ft below GL, weld on plate, 5 sks cement each in rat hole and mouse hole. |
| Agency | Form: (02) 401852443 12/27/2018 | Bradenhead tests shall be performed and reported according to the following schedule and Form 17 submitted within 10 days of each test.:
1) All: Within 60 days of rig release, prior to stimulation.
2) Delayed completion: 6 months after rig release, prior to stimulation.
3) All: Within 30 days of first production, as reported on Form 5A. |