Engineer | Form: (02 ) 400193338 8/17/2011 | 1) Provide 24 hour notice of MIRU to Craig Quint at 719-767-8939 or e-mail at craig.quint@state.co.us.
2) If production casing is set provide cement coverage to at least 200’ above the Marmaton, and stage cement Cheyenne/Dakota (4500’-3950’ minimum). Run and submit CBL to verify cemented intervals.
3) If well is a dry hole set plugs at the following depths: 40 sks cement +/- 50’ above the Marmaton, 40 sks cement across any DST w/ show, 40 sks cement 50’ below Cheyenne (4500’ up), 40 sks cement 50’ above top of Dakota (3950’ up), 50 sks cement from 50’ below surface casing shoe up into surface casing, 15 sks cement in top of surface casing, cut 4 ft below GL, weld on plate, 5 sks cement each in rat hole and mouse hole.
|
Permit | Form: (04 ) 400534313 1/6/2014 | A new form 2 needed since permit expired and the Torch is a new formation objective. |
Permit | Form: (02 ) 400534697 2/4/2014 | Operator shall comply with Buffer Zone Move-In, Rig-Up Notice Policy dated 12-16-2013. |
Permit | Form: (02 ) 400534697 2/4/2014 | Open hole resistivity and gamma logs shall be run to describe the stratigraphy of the entire well bore and to adequately verify the setting depth of surface casing and aquifer coverage. On a multi-well pad, these open hole logs are only required on one of the first wells drilled on the pad and the Drilling Completion Report - Form 5 for every well on the pad shall identify which well was logged. |
Environmental | Form: (04 ) 400961329 12/31/2015 | Operator will submit Form 27 remediation plan by February 29, 2016. No form 19 spill report will be required. |
Reclamation Specialist | Form: (04 ) 401294500 5/31/2017 | Approval/passing of the form 4 acknowledges that the Oil and Gas Conservation Commission has received the Notice. It is not an acknowledgement that inspection has been passed. A field inspection will be conducted to evaluate compliance with COGCC standards. |
Reclamation Specialist | Form: (04 ) 402822671 12/20/2021 | COGCC will not require further action at this time. If any future disturbances (i.e., subsequent operations) affect interim reclamation vegetation, Operator shall reclaim all disturbances as early as practicable to meet Rule 1003 standards. Should future conditions at the site indicate poor growth that is not reflective of reference areas, then further investigation and reclamation activities may be required. |