Permit | Form: (06 ) 402509377 10/19/2020 | Submit Form 5A to report perfed intervals for the Niobrara identified on the wellbore diagram attached to this Notice of Intent. Include wireline tickets and/or cement tickets. This Form 5A must be submitted within 30 days for compliance with Rule 308B. |
Engineer | Form: (06 ) 402509377 10/28/2020 | It appears the well was refraced in 2015 and Niobrara perfs may have been added at that time. Include details on previously requested 5A. |
Engineer | Form: (06 ) 402509377 10/28/2020 | Plugging
1) Provide 48 hour notice of plugging MIRU via electronic Form 42.
2) Properly abandon flowlines as per Rule 1105. File electronic Form 42 once abandonment complete. Within 90 days of an operator completing abandonment requirements for an off-location flowline or crude oil transfer line the operator must submit a Flowline Report, Form 44.
3) Plugs and squeezes will be placed as stated in the Plugging Procedure section of the approved NOIA unless revised by COA or prior approval from COGCC is obtained.
4) The wellbore must be static prior to placing cement plugs which are to be a minimum of 100' in length for all but surface plugs. Mechanical isolation requires a 25' cement plug, minimum. For plugs not specified to be tagged, a tag is required if circulation is not maintained while pumping plug and displacing to depth.
5) Place a 50' plug (minimum) at the surface, both inside the inner most casing and in all annular spaces. Surface plugs shall be circulated to surface. Confirm cement to surface in all strings during cut and cap.
6) With the Form 6 SRA operator must provide written documentation which positively affirms each COA has been addressed.
7) Contact COGCC Area Inspector prior to commencing plugging operations.
8) After placing the shallowest hydrocarbon isolating plug (7870'), operator must wait a sufficient time on all subsequent plugs to confirm static conditions. If at any time after placing this plug there is evidence of pressure or of fluid migration, contact COGCC Area Engineer before continuing operations.
9) No current Form 17 on file with COGCC. Contact COGCC area engineer with results of pre-plugging bradenhead test for confirmation of plugging procedure prior to commencing plugging operations.
10) Wait 8 hours after pumping plug at 2800-2500’ and tag, in order to assure that there is no pressure or flow before proceeding with plugging operations. Contact COGCC Area Engineer if well is not static after waiting the 8 hours.
11) File Form 5A for refrac in 2015. |
Engineer | Form: (06 ) 402509377 10/28/2020 | Bradenhead Testing
Prior to starting plugging operations a bradenhead test shall be performed if there has not been a reported bradenhead test within the 60 days immediately preceding the start of plugging operations.
1) If, before opening the bradenhead valve, the beginning pressure is greater than 25 psi, sampling is required.
2) If pressure remains at the conclusion of the test, or if any liquids were present during the test, sampling is required.
The Form 17 shall be submitted within 10 days of the test. Sampling shall comply with Operator Guidance - Bradenhead Testing and Reporting Instructions. If samples are collected, copies of all final laboratory analytical results shall be provided to the COGCC within three (3) months of collecting the samples.
If there is a need for sampling, contact COGCC engineering for verification of plugging procedure. |
Engineer | Form: (06 ) 402509377 10/28/2020 | Venting
Operator shall implement measures to control unnecessary and excessive venting, to protect the health and safety of the public, and to ensure that vapors and odors from well plugging operations do not constitute a nuisance or hazard to public welfare. |