Engineer | Form: (06 ) 401429061 10/27/2017 | If there has not been a Bradenhead test within 60 days of plugging this well,prior to starting plugging operations a bradenhead test shall be performed. If the well was not sampled as part of a prior test it should be sampled if pressure is 25# or greater.
1) If, before opening the bradenhead valve, the beginning pressure is greater than 25 psi, sampling is required.
2) If pressure remains at the conclusion of the test, or if any liquids were present during the test, sampling is required.
Sampling shall comply with Operator Guidance - Bradenhead Testing and Reporting Instructions, Appendix A: Liquid and Gas Sampling.
The Form 17 shall be submitted within 10 days of the test.
|
Engineer | Form: (06 ) 401429061 10/27/2017 | NOTE: Changes in plugging procedure - stub plug at 1970' increased quantity to 466 sx, this plug needs to be tagged at 317' or shallower.
1) Provide 48 hour notice of plugging MIRU via electronic Form 42.
2) Properly abandon flowlines as per Rule 1103. File electronic Form 42 once abandonment complete.
|