| Engineer | Form: (06) 402284220 01/16/2020 | Operator shall implement measures to control venting, to protect health and safety, and to ensure that vapors and odors from well plugging operations do not constitute a nuisance or hazard to public welfare. |
| Engineer | Form: (06) 402284220 01/16/2020 | 1) Provide 48 hour notice of plugging MIRU via electronic Form 42.
2) Prior to placing the 1576' plug: verify that all fluid migration (liquid or gas) has been eliminated. If evidence of fluid migration or pressure remains, contact COGCC Engineer for an update to plugging orders.
3) After isolation has been verified, pump plug and displace. If cement is not circulated to surface, shut-in, WOC 4 hours then tag plug – must be at 351' or shallower and provide 10 sack plug at surface.
4) Leave at least 100’ of cement in the wellbore for each plug.
5) Properly abandon on-location flowlines as per Rule 1105. File electronic Form 42 once abandonment is complete. Within 30 days of an operator completing abandonment requirements for an off-location flowline or crude oil transfer line, the operator must submit a Flowline Report, Form 44.
6) With the Form 6 SRA operator must provide written documentation which positively affirms each COA has been addressed.
7) After placing the shallowest hydrocarbon isolating plug (7200'), operator must wait a sufficient time to confirm static conditions. If at any time after placing this plug there is evidence of pressure or of fluid migration, contact COGCC engineering before continuing operations. |
| Engineer | Form: (06) 402284220 01/16/2020 | If there has not been a reported Bradenhead test within 60 days of plugging this well, prior to starting plugging operations, a Bradenhead test shall be performed.
1) If, before opening the Bradenhead valve, the beginning pressure is greater than 25
psi, sampling is required, and the COGCC engineering staff must be contacted.
2) If pressure remains at the conclusion of the test, or if any liquids were present during
the test, sampling is required.
3) If sampling is required contact COGCC engineering for a confirmation of plugging
requirements prior to placing any plugs.
Sampling shall comply with Operator Guidance - Bradenhead Testing and Reporting
Instructions.
The Form 17 shall be submitted within 10 days of the test. |
| Engineer | Form: (06) 402284220 01/22/2020 | Added CIBP at 7200' with 2 sacks on top. Operator concurs. |
| Engineer | Form: (04) 403744366 04/08/2024 | 1. Operator shall implement measures to control venting, to protect health and safety, and to ensure that vapors and odors from well operations do not constitute a nuisance or hazard to public welfare.
2. Bradenhead gas is not to be vented to the atmosphere; any gas from the Bradenhead will be routed to the specified abatement system. Shut in bradenhead pressure shall not exceed 50 psig. Operator shall implement measures to get an estimate of the gas flow rate and/or volume from the bradenhead.
3. Within thirty days of 10/08/2024, submit a Form 4 Sundry that summarizes current well condition. The sundry should include details of the future plans, sample analysis interpretation, bradenhead test description, and the flow rate information and pressure data.
4. Shut well in for at least seven days to monitor build up pressures then conduct a new bradenhead test and submit the Form 17 within ten days of the test.
5. If a sample has not been collected from surface casing within the last twelve months collect bradenhead gas samples for laboratory analysis. Sampling shall comply with Operator Guidance - Bradenhead Testing and Reporting Instructions, Appendix A: Liquid and Gas Sampling. Copies of all final laboratory analytical results shall be provided to the ECMC within three months of collecting the samples. |
| OGLA | Form: (06) 403825831 06/24/2024 | Operator will consult with CPW when plugging and abandonment (PA) of wells located within CPW-owned State Parks and State Wildlife Areas (SWA) to develop measures to avoid, minimize, and mitigate conflicts during hunting seasons that may arise between hunters and site operations. |
| OGLA | Form: (06) 403825831 06/24/2024 | Operator will implement measures to capture, combust, or control emissions to protect health and safety, and to ensure that vapors and odors from well plugging operations do not constitute a nuisance or hazard to public health, welfare and the environment. Due to the proximity of residential building units (RBUs) all blowdown gasses will be controlled.
Due to proximity of plugging and abandonment (P&A) operations to BUs, operator will comply with Table 423 Maximum Permissible Noise Levels for residential land use. Prior to initiating work, operator will install temporary sound walls, straw bales, or other BMPs to dampen noise if necessary for compliance.
Due to close proximity to Residential Building Units (RBUs), prior to commencing operations, at a minimum, the operator will provide an informational sheet to the owners/occupants of the RBUs nearby and adjacent to the parcel with the well. The sheet will include the operator's contact information and the nature, timing, and expected duration of the P&A operations. |
| Engineer | Form: (06) 403825831 07/11/2024 | 1) Provide electronic Form 42 Notice of MIRU 2 business days ahead of operations and electronic Form 42 Notice of Plugging Operations 48 hours prior to mobilizing for plugging operations. These are two separate notifications, required by Rules 405.e and 405.l.
2) Prior to placing cement above the base of the Upper Pierre (2500') : verify that all fluid (liquid and gas) migration has been eliminated. If evidence of fluid migration or pressure remains, contact ECMC Engineer for an update to plugging orders.
3) Pump surface casing shoe plug at 1626' only after isolation has been verified. If surface casing cement is not circulated to surface, shut-in, WOC 4 hours then tag plug – must be at 1306' or shallower and provide a minimum of 10 sx plug at the surface.
4) Leave at least 100’ of cement in the wellbore for each plug without mechanical isolation.
5) After cut and prior to cap, verify isolation by either a 15 minute bubble test or 15 minute optical gas imaging recording. If there is indication of flow contact ECMC Engineering. Provide a statement on the 6SRA which method was used and what was observed. Retain records of final isolation test for 5 years.
6) With the Form 6 SRA operator must provide written documentation which positively affirms each COA listed above has been addressed. |
| Engineer | Form: (06) 403825831 07/11/2024 | Consistent with Rule 911.a, a Form 27 must be approved prior to cut and cap, conducting flowline abandonment, or removing production equipment. Allow 30 days for Director review of the Form 27; include the Form 27 document number on the Form 44 for offsite flowline abandonment (if applicable) and on the Form 6 Subsequent.
Properly abandon flowlines per Rule 1105. If flowlines will be abandoned in place, include with the Form 27: pressure test results conducted in the prior 12 months as well as identification of any document numbers for a ECMC Spill/Release Report, Form 19, associated with the abandoned line. |
| Engineer | Form: (06) 403825831 07/11/2024 | Prior to starting plugging operations a bradenhead test shall be performed if there has not been a reported bradenhead test within the 60 days immediately preceding the start of plugging operations.
1) If, before opening the bradenhead valve, the beginning pressure is greater than 25 psi, sampling is required.
2) If pressure remains at the conclusion of the test, or if any liquids were present during the test, sampling is required.
The Form 17 shall be submitted within 10 days of the test. Sampling shall comply with Operator Guidance - Bradenhead Testing and Reporting Instructions. If samples are collected, copies of all final laboratory analytical results shall be provided to the ECMC within three (3) months of collecting the samples.
If there is a need for sampling, contact ECMC engineering for verification of plugging procedure. |
| Engineer | Form: (06) 403825831 07/11/2024 | WITH KNOWN BRADENHEAD PRESSURE
After placing plug at 3100' assure that all fluid migration has been eliminated by monitoring the well for a minimum of 8 hours before proceeding to the next plug. If at any time after placing this plug there is evidence of pressure or of fluid migration, contact ECMC engineering before continuing operations. |