WELL05-123-05952PETERS
3
8 NORTH LLC
10575
PA
7/19/2022
FURY
27925
WELD  123
NENW 33 12N61W 6
317524View Related Related
 
Form 27/27AView Related Related View DocsDoc
Date Submitted:1/27/2022
Date Recv'd:1/27/2022Assigned by:Rob Young
DocNum:402938601API number:05-123-05952
Document Type:FORM 27 Project Number:22166
Operator Information:
Operator:8 NORTH LLC
Oper. No.10575
Address:555 17TH STREET SUITE 3700  DENVER  CO 80202
Type Of Facility:SPILL OR RELEASE
Fac. NamePETERS-612N61W
County Name:WELD
Operator contact:Jacob Evans
qtrqtr: SESEsection: 33township: 12Nrange: 61Wmeridian: 6
Remediation Details:
Impacted Media
MediaImpactedExtentHow Determined?
SOILS UNo known impacts Investigation pending
Reason for Report: OTHER
Cause of Condition: OTHER
Potential Receptors: Plains sharp-tailed grouse production area and pronghorn winter concentration.
 
HOW REMEDIATE:  As needed, site specific soil and/or groundwater remediation plans will be developed and submitted to COGCC via supplemental Form 27.
 
INITIAL ACTION:  This form has been prepared to support removal of a wellhead and off-location flowline. Soil samples will be field screened utilizing a photoionization detector, as well as olfactory and visual senses, at approximately the locations indicated on the attached proposed soil sample locations diagram. Soil samples collected beneath the off-location flowline will be field-screened and submitted only if impacts are suspected. Additionally, soil samples from the flowline will be collected and submitted for laboratory analysis from specific areas of concern: where subsurface piping connects to surface equipment, where Above Ground Storage Tanks (AST), valves, pumps, compressors, or other process equipment were used on a location, and/or at joints, hammer unions, or previous repairs in above ground or subsurface pipe, if present. Grab samples will be collected and field-screened from the base and each sidewall of the excavation to cut and cap the wellhead. At least one sample, either the highest PID result or the base, will be submitted for laboratory analysis. Initial laboratory soil analysis will include BTEX, 1,2,4 and 1,3,5 Trimethylbenzene, naphthalene, TPH, pH, EC, SAR and boron. Samples will be submitted to a NELAP accredited laboratory using COGCC approved analysis methods. Any identified impacts will be reported as required for each discovery via Form 19 submittal.
 
RECLAMATION PLAN:  Reclamation activities will be completed in accordance with 1000 Series Rules, in collaboration with the landowner, and reported in a Form 4 (Sundry Notice) with proper documentation to demonstrate compliance with requirements for final reclamation. After all road base or other material is removed for reclamation, Operator may submit samples for laboratory analysis for soil suitability in compliance with 915.b if impacts from inorganic constituents are indicated.
 
SOURCE REMOVED:  If a suspected release is identified and confirmed through soil screening and/or laboratory analysis during decommissioning of this facility, soils may be removed and transported to a licensed disposal facility. Transport and disposal records will be kept on file under usual and customary practice and are available upon request. If all source material cannot be removed during excavation activities, additional methodologies will be proposed in subsequent Form 27 supplementals.
 
Correspondence Log:
Final Resolution
DateCase Closed?Letter Sent?CECMC Person
N/ANKrystal Heibel
N/ANRob Young
N/ANKrystal Heibel
N/ANKrystal Heibel
N/ANKrystal Heibel
N/ANRob Young
N/ANLaurel Anderson
N/ANKrystal Heibel
N/ANKrystal Heibel
 
Coordinates:
TypeFacility IDFacility Name/NumLat/Long
Remediation-99999No Facility
1
40.971150/-104.212910

Remediation481792PETERS-612N61W
40.958322/-104.203712