Storm Water/Erosion Control | Form: (02A ) 402156151 3/10/2020 | Operator will control construction storm water discharge in a manner consistent with good engineering practices to prevent offsite migration of contaminant/sediment. BMPs consisting of an 18" diversion ditch, seeding and mulching (SM), culvert inlet protection (ICP), erosion control blankets (ECB), sediment control logs (SCL), sediment basins, and silt fence will be installed as BMPs to prevent degradation and control sedimentation. |
Material Handling and Spill Prevention | Form: (02A ) 402156151 3/10/2020 | All facilities will be equipped with remote monitoring and remote shut down, which includes isolation at the well head. Engineered liner systems will be used in secondary steel containment systems for tank batteries. Pollution control containers (spill boxes) will be used on truck loading lines and placed within the limits of the secondary containment system. Automatic shutdown level devices will be installed on each tank with remote monitoring capabilities. Automatic shutdown level devices will be installed on all pressure vessels and liquid knockouts. Automatic shutdown pressure devices will be installed on flowlines from well heads to facilities with remote monitoring capabilities. Additionally, cathodic protection will be used on buried steel lines to mitigate corrosion. Automatic shutdown pressure devices will be installed on process vessels with remote monitoring capabilities. |
Material Handling and Spill Prevention | Form: (02A ) 402156151 3/10/2020 | Preventative maintenance and best practices will be in place to prevent leaks from vessels including:
• Yearly shut-downs and visual inspections of each 2-phase and 3-phase vessel on site
• Yearly NDT (Non-Destructive Testing) of each 2-Phase and 3-Phase vessel shell and head on site
• Vessels that fail this test are removed from service
• Conservative corrosion allowances
• Internal coating to prevent corrosion
• Semi-Annual PSV testing
• Weekly environmental checks by operations personnel (weekly at a minimum)
• NDT of all water piping to prevent leaks due to corrosion
• NDT spot checking of various flowlines to monitor for thin walled piping due to erosion or corrosion
• Yearly test of all devices that shut down the facility |
Material Handling and Spill Prevention | Form: (02A ) 402156151 3/10/2020 | A containment system capable of containing one and one-half times (150%) the capacity of the largest vessel, plus sufficient freeboard to prevent overflow will be constructed around all permanent tanks at this Location. The containment system will be constructed of a steel-rim berm and lined with a synthetic or engineered liner, mechanically connected to the steel-rim which will surround all primary containment vessels. When used, temporary vessels will have secondary containment constructed from lined earthen berms or pre-engineered, duck-pond style containment systems. All berms and containment devices will be inspected quarterly. |