COGIS - Conditions of Approval Results
TypeSource DocumentConditions of Approval
OGLAForm: (02A)
401297061
07/14/2017
Location lies within proximity to a surface water drainage. Operator Shall employ tertiary containment along the cross- and down-gradient perimeters of the Location.
 
COGIS - Best Management Practice Results
BMP TypeSource DocumentBest Management Practices
ConstructionForm: (02A )
401297061
8/20/2017
Prior to construction, perimeter controls will be installed utilizing cuttings from the clearing operations. Once the well pad has been constructed a variety of BMP's shall be utilized for the site specific conditions. BMP's to be utilized may include, but are not limited to: -Dirt Ditch/Berm -Erosion Control Blankets -Straw Bale Barrier -Straw Wattles -Seeding -Imported Hard Armor -Check Dams -Culvert/Culvert Protection -Crimped Straw -Silt Fence -Surface Roughening/Surface Rip During construction, site will be inspected every 14 days and 24-72 hours after any precipitation event causing erosion depending on the current site activities. These inspections will be recorded and maintained at Nighthawk's office. Repairs shall be completed as soon as possible after an inspection reporting BMP repairs are required. Any site specific modifications will be revised on the site plan when implemented at the site. A field wide Stormwater Management Plan (SWMP) for the Project Area is located at Nighthawk's office. Spill Protection Control and Countermeasures (SPCC) plans for the Project Area are stored on file at Nighthawk's office. The field wide SWMP addresses SPCC during construction operations.
ConstructionForm: (02A )
401853523
2/12/2019
Prior to construction, perimeter controls will be installed utilizing cuttings from the clearing operations. Once the well pad has been constructed, a variety of BMP's shall be utilized for the site-specific conditions. BMP's to be utilized may include, but not limited to: -Dirt Ditch/Berm -Erosion Control Blankets -Straw Bale Barrier -Seeding -Imported Hard Armor -Check Dams -Culvert/ Culvert Protection -Crimped Straw -Silt Fence -Surface Roughening/Surface Rip During Construction, site will be inspected every 14 days and 24-72 hours after any precipitation event causing erosion depending on the current site activities. These inspections will be recorded and maintained at D90's office. Repairs shall be completed as soon as possible after an inspection reporting BMP repairs are required. A site-specific modification will be revised on the site plan when implemented at the site.