Skip to Main Content

COGIS DB

 
Facility TypeFacility ID/
API
Facility Name/
Number
Operator Name/
Number
StatusField Name/
Number
LocationLocation IDRelated Facilities
LOCATION451166Big Sandy 3-65 36-31
CRESTONE PEAK RESOURCES OPERATING LLC
10633
AC
8/1/2024
WILDCAT
99999
AURORA/ADAMS  001
NESE 35 3S65W 6
451166View Related
 
COGIS - Conditions of Approval Results
TypeSource DocumentConditions of Approval
OGLAForm: (02A )
401151934
4/18/2017
Interim Reclamation will be evaluated by well count at the time of completion of the wells currently permitted on this Form 2A.
OGLAForm: (02A )
401365983
9/7/2017
Operator shall comply with 1000-Series Rules for Interim Reclamation. All areas not in use for production activities shall be reclaimed in accordance with the 1000-Series Rules within 6 months of the spud date for the approved well. In the event, additional operations are to occur within 12 months of the spud date, Operator shall submit a Rig Schedule showing a scheduled timeline of additional drilling operations via Form 4 Sundry. If additional drilling operations have not commenced at 12 months, Operator shall submit a Variance Request via Form 4 Sundry for compliance with additional bonding requirements as identified in the NTO for Interim Reclamation prior to the 12 month deadline.
OGLAForm: (02A )
401365983
9/7/2017
Operator shall comply with all requirements as set forth in the COGCC Notice to Operators for Interim Reclamation.
OGLAForm: (02A )
402289761
8/11/2020
Operator shall submit additional Location Pictures showing greater interior of the Location and individual facilities via Form 4 Sundry, within 45 days upon receipt of this Amended Form 2A.
OGLAForm: (04 )
403134963
8/15/2022
Operator will implement measures to capture, combust, or control emissions to protect health and safety, and to ensure that vapors and odors from well completion(s), well repair/maintenance, well perforating, temporary abandonment activities, additional equipment installation, and/or testing operations with a workover rig, wireline rig, or other heavy equipment do not constitute a nuisance or hazard to public health, welfare and the environment. Due to proximity of building units (BUs) all blowdown gases will be controlled.
 
COGIS - Best Management Practice Results
BMP TypeSource DocumentBest Management Practices
Storm Water/Erosion ControlForm: (02A )
402289761
9/4/2020
Opepartor will install stormwater controls around the perimeter of the location prior to construction and will include a stormwater detention pond in the northeast corner of the Location and a berm and ditch system. They will remain in place through final reclamation or until pad is stabilized.
Material Handling and Spill PreventionForm: (02A )
402289761
9/4/2020
Secondary Containment All facilities will be equipped with remote monitoring and remote shut down, which includes isolation at the well head. Engineered liner systems will be used in secondary steel containment systems for tank batteries. Pollution control containers (spill boxes) will be used on truck loading lines and placed within the limits of the secondary containment system. Automatic shutdown level devices will be installed on each tank with remote monitoring capabilities. Automatic shutdown level devices will be installed on all pressure vessels and liquid knockouts. Automatic shutdown pressure devices will be installed on flowlines from well heads to facilities with remote monitoring capabilities. Additionally, cathodic protection will be used on buried steel lines to mitigate corrosion. Automatic shutdown pressure devices will be installed on process vessels with remote monitoring capabilities.
Emissions mitigationForm: (02A )
402289761
9/4/2020
Emissions Controls Combustors will be available at the Location during the entire production phase to eliminate fugitive emissions in the event of maintenance or emergency use. The device will be fired using natural gas and operate with a 98% or higher hydrocarbon destruction efficiency. The device will be designed and operated in a manner that will ensure no visible emissions during normal operation. Test separators and associated flow lines, sand traps and emission control systems shall be installed on-site to accommodate green completions techniques. When commercial quantities of salable quality gas are achieved at each well, the gas shall be immediately directed to a sales line or shut in and conserved. If a sales line is unavailable or other conditions prevent placing the gas into a sales line, Operator shall not produce the wells without an approved variance per Rule 805.b.(3)C.