| Planning | Form: (02A ) 400894377 12/17/2015 | 604c.(2).E. Multi-Well Pads: In order to reduce surface impact, this application is for a
9-well pad. |
| Planning | Form: (02A ) 400894377 12/17/2015 | 604c.(2).Q. Guy Line Anchors: Should guy line anchors be left buried for future use,
they shall be identified by a bright marker greater than four (4) feet high and no more
than one (1) foot east of the guy line anchor. |
| Planning | Form: (02A ) 400894377 12/17/2015 | 604c.(2).R. Tank Specifications: Two 500 barrel skid-mounted frac tanks will be
temporarily placed on-site for use of the pre-spud rig only. One tank will store water
and the other will store water based mud. |
| Planning | Form: (02A ) 400894377 12/17/2015 | 604c.(2).S. Access Roads: KMG will utilize a lease access road from CR 23 for drilling
and production operations and maintenance equipment. The road will be properly
constructed and maintained to accommodate for local emergency vehicle access. |
| Community Outreach and Notification | Form: (02A ) 400894377 12/17/2015 | 305.a.(2) A Notice of Intent to Conduct Operations was sent to each building unit
owner within the Exception Zone or Buffer Zone Setback. Recipients did not contact
KMG.
As a part of planning this proposed location, Kerr-McGee held multi-disciplinary
Surface Impact Planning Meetings regarding the impacts and mitigations associated
with this proposed location. The toll-free hotline number and email for the Anadarko
Colorado Response Line will be posted at the entrance to the lease access road for
stakeholders during drilling and completion operations at this proposed location.
Courtesy Notifications will be sent to impacted stakeholders prior to drilling operations
and again prior to completions operations, providing contact information for the
Anadarko Colorado Response Line and online resources. |
| Traffic control | Form: (02A ) 400894377 12/17/2015 | 604c.(2).D. Traffic Plan: If required by the local government, a traffic plan will be
coordinated with the local jurisdiction prior to commencement of operations. |
| General Housekeeping | Form: (02A ) 400894377 12/17/2015 | 604c.(2).O. Loadlines: All loadlines shall be bullplugged or capped. |
| General Housekeeping | Form: (02A ) 400894377 12/17/2015 | 604c.(2).P. Removal of Surface Trash: A commercial size trash bin for removing debris
will be located on site. This bin will be for use by all parties affiliated with the
operation. |
| Storm Water/Erosion Control | Form: (02A ) 400894377 12/17/2015 | 604c.(2).G. Berm Construction: Kerr-McGee will create tertiary containment by
construction of a berm or diversion dike, site grading, or other comparable measures
sufficient to further protect the following:
Ditch: 15' to south
Ditch: 103' to south
Ditch: 546' to NNW
Pond: 695' to ENE |
| Storm Water/Erosion Control | Form: (02A ) 400894377 12/17/2015 | 604c.(2).W. Site-Specific Measures: KMG maintains a Storm Water Management
Plan that assesses erosion control for every KMG operated location. This location will
be added to this plan once construction begins. This site will be inspected every
fourteen (14) days during construction activities, every twenty-eight (28) days after
construction is completed, and after any major weather event. |
| Material Handling and Spill Prevention | Form: (02A ) 400894377 12/17/2015 | 604c.(2).N. Control of Fire Hazards: KMG and its contractors will employ best
management practices during the drilling and production of its wells and facilities and
will comply with appropriate COGCC rules concerning safety and fire. KMG will
ensure that any material that might be deemed a fire hazard will remain no less than
twenty-five (25) feet from the wellhead(s), tanks and separator(s). |
| Dust control | Form: (02A ) 400894377 12/17/2015 | 805.c. Dust: Water will be placed on dirt access roads to mitigate dust as needed. If
feasible, magnesium chloride will also be used as needed on access roads to further
abate dust. |
| Construction | Form: (02A ) 400894377 12/17/2015 | 604c.(2).M. Fencing Requirements: The completed wellsites will be surrounded with a
fence and gate with adequate lock to restrict access to authorized personnel only.
KMG personnel will monitor the wellsites regularly upon completion of the wells.
Authorized representatives and/or KMG personnel shall be on-site during drilling and
completion operations. |
| Noise mitigation | Form: (02A ) 400894377 12/17/2015 | 604c.(2).A. Noise: Sound surveys have been conducted on each rig type and are
utilized to anticipate any additional effective noise mitigation once a drilling rig is
determined.
Pending a safety review after construction of the location, sound mitigation barriers
(straw bales) will be placed along the perimeter of the pad location to damper noise
during drilling and completions to the nearby residences and to Weld County Roads 5
and 23. |
| Drilling/Completion Operations | Form: (02A ) 400894377 12/17/2015 | 604c.(2).B. Closed Loop Drilling System: KMG will use a closed loop or “pitless”
system for drilling and fluid management and will not construct a reserve pit. |
| Drilling/Completion Operations | Form: (02A ) 400894377 12/17/2015 | 604c.(2).C. Green Completions: Temporary above ground polyethylene water
pipelines will deliver water to location operations from larger trunk lines to reduce truck
traffic and minimize air pollution. Pipeline infrastructure is in place prior to completions
operations to ensure saleable gas, once hydrocarbons are cut, is sent directly to sales
without flaring during flowback. |
| Drilling/Completion Operations | Form: (02A ) 400894377 12/17/2015 | 604c.(2).H. BOPE: Our rigs at a minimum will have a double ram with blind and pipe
ram and annular preventer. |
| Drilling/Completion Operations | Form: (02A ) 400894377 12/17/2015 | 604c.(2).I. BOPE Testing for Drilling Operations: Upon initial rig-up, BOPEs will be
tested at a minimum of every 30 days. |
| Drilling/Completion Operations | Form: (02A ) 400894377 12/17/2015 | 604c.(2).J. BOPE for Well Servicing Operations: Blowout prevention equipment will be
used on any servicing operations associated with this well. Backup stabbing valves will
be used during any future servicing operations during reverse circulation. Valves shall
be pressure tested before each well servicing operation using low-pressure air and
high-pressure fluid. |
| Drilling/Completion Operations | Form: (02A ) 400894377 12/17/2015 | 604c.(2).K. Pit Level Indicators: All storage tanks used for active drilling operations
(used in lieu of pits) contain pit level monitors with Electronic Drilling Recorders (EDR).
KMG uses EDRs with pit level monitor(s) and alarm(s) for production rigs. Basic level
gauges are used on tanks utilized for the surface rig. |
| Drilling/Completion Operations | Form: (02A ) 400894377 12/17/2015 | 604c.(2).L. Drill Stem Tests: No drill stem tests are planned and none will be
performed without prior approval from the Director. |
| Drilling/Completion Operations | Form: (02A ) 400894377 12/17/2015 | 803. Lighting: To the extent practicable, site lighting shall be shielded and directed
downward and inward toward operations to avoid glare on public roads and nearby
Building Units. |
| Final Reclamation | Form: (02A ) 400894377 12/17/2015 | 604c.(2).T. Well Site Cleared: The wellsite will be cleared of all non-essential
equipment within ninety (90) days after all wells associated with the pad have been
plugged and abandoned. |
| Final Reclamation | Form: (02A ) 400894377 12/17/2015 | 604c.(2).U. Identification of Plugged and Abandoned Wells: Pursuant to rule 319.a.(5).,
once the well has been plugged and abandoned, KMG will identify the location of the
wellbore with a permanent monument that will detail the well name and date of
plugging. |