| OGLA | Form: (02A) 400529371 12/10/2014 | Notify the COGCC 48 hours prior to start of pad reconstruction/regarding, rig mobilization, spud, pipeline testing, start of hydraulic stimulation operations, and start of flowback operations (if different than hydraulic stimulation operations) using Form 42 (the appropriate COGCC individuals will automatically be email notified, including the LGD for hydraulic stimulation operations). |
| OGLA | Form: (02A) 400529371 12/10/2014 | Operator must ensure secondary containment for any volume of fluids contained at tank site during operations; including, but not limited to, construction of a berm or diversion dike, diversion/collection trenches within and/or outside of berms/dikes, site grading, or other comparable measures (i.e., best management practices (BMPs) associated with stormwater management) sufficiently protective of nearby surface water. Any berm constructed at the well pad location will be stabilized, inspected at regular intervals (at least every 14 days and after precipitation events), and maintained in good condition. |
| OGLA | Form: (02A) 400529371 12/10/2014 | The moisture content of drill cuttings managed onsite shall be kept as low as practicable to prevent accumulation of liquids greater than de minimis amounts. After drilling and completion operations have been completed, the drill cuttings that will remain on the well pad location (cuttings management area, the cut portion of the pad, cuttings trench, dry cuttings drilling pit), must meet the applicable standards of Table 910-1. After the drill cuttings have been amended (if necessary) and placed on the well pad, sampling frequency of the drill cuttings (to be determined by the operator) shall be representative of the material left on location. No offsite disposal of cuttings to another oil and gas location shall occur without prior approval of a Waste Management Plan (submitted via a Form 4 Sundry Notice) specifying disposal location and waste characterization method. Commercial disposal of drill cuttings will only require notification to COGCC via a Form 4 Sundry Notice.
If the well(s) is(are) to be hydraulically stimulated, flowback and stimulation fluids must be sent to tanks, separators, or other containment/filtering equipment before the fluids can be placed into any pipeline or storage vessel located on the well pad; or into tanker trucks for offsite disposal. The flowback and stimulation fluid tanks, separators, or other containment/filtering equipment must be placed on the well pad in an area constructed to be sufficiently impervious to contain any spilled or released material.
Potential odors associated with the completions process and/or with long term production operations must be controlled/mitigated. |
| OGLA | Form: (02A) 400529371 12/10/2014 | Operator shall pressure test pipelines in accordance with Rule 1101.e.(1) prior to putting into initial service any temporary surface or permanent buried pipelines and following any reconfiguration of the pipeline network.
Operator must routinely inspect the entire length of the surface pipeline to ensure integrity. Operator shall conduct daily inspections of surface poly pipeline routes for leaks during active transfer of fluids and implement best management practices to contain any unintentional release of fluids along all portions of the surface pipeline route where temporary pumps and other necessary equipment are located. Inspections shall be conducted by viewing the length of the pipeline; operator will endeavor to minimize surface disturbance during pipeline monitoring. In addition, pump stations along the surface poly or steel pipeline route will be continuously monitored when operating in order to swiftly respond to such a failure.
Operator will implement BMPs necessary to mitigate a potential for a release of fluids to impact streams, intermittent streams, ditches, and drainage crossings. For these crossings: if poly pipe is used on the surface, operator will ensure appropriate containment by either installing over-sized pipe “sleeves” which extend the length of the crossing and beyond to a distance deemed adequate to capture (catchment basins) and/or divert any possible release of fluids and prevent fluids from reaching the stream or drainage; installing over-sized pipe “sleeves” which extend the length of the crossing and installing shut off valves on either side of crossing instead of catchment basins; or develop an alternative means for containment. For all other pipeline materials, operator will implement BMPs necessary to mitigate a potential for E&P fluids not to reach groundwater or flowing surface water.
Operator will utilize, to the extent practical, all existing access and other public roads, and/or existing pipeline right-of-ways, when placing/routing the temporary surface pipelines. This will reduce surface disturbance and fragmentation of wildlife habitat in the area. |
| Permit | Form: (02A) 401189822 05/04/2017 | Minimize the number, length, and footprint of oil and gas development roads.
Combine utility infrastructure (gas, electric, and water) planning with roadway planning
to avoid separate utility corridors.
Combine and share roads to minimize habitat fragmentation.
Where possible, consolidate pipeline and existing roadways, or roadways that are
planned for development.
Maximize the use of directional drilling to minimize habitat loss/fragmentation.
Maximize use of remote telemetry for well monitoring to minimize traffic . |
| Permit | Form: (02A) 401189822 05/04/2017 | Use only certified weed-free native seed in seed mixes, except for non-native plants
that benefit wildlife.
WPX Energy will use certified, weed free grass hay, straw, hay or other mulch
materials used for the reseeding and
reclamation of disturbed areas.
Install exclusionary devices to prevent bird and other wildlife access to equipment
stacks, vents and openings.
Reduce visits to well-sites through remote monitoring (i.e. SCADA) and the use of
multi-function contractors. |
| OGLA | Form: (02A) 401189822 05/04/2017 | Operator shall pressure test pipelines (flowlines from wellheads to separators to tanks; pipelines from onsite separators to offsite storage tanks, and any temporary surface lines used for hydraulic stimulation and/or flowback operations) in accordance with Rule 1101.e.(1) prior to putting into initial service any temporary surface or permanent buried pipelines and following any reconfiguration of the pipeline network, and tested annually, unless agreed to by both parties that the flowlines can be managed under an approved COGCC variance.
Operator must routinely inspect the entire length of the surface pipeline to ensure integrity. Operator shall conduct daily inspections of surface poly pipeline routes for leaks during active transfer of fluids and implement best management practices to contain any unintentional release of fluids along all portions of the surface pipeline route where temporary pumps and other necessary equipment are located. Inspections shall be conducted by viewing the length of the pipeline; operator will endeavor to minimize surface disturbance during pipeline monitoring. In addition, pump stations along the surface poly or steel pipeline route will be continuously monitored when operating in order to swiftly respond to such a failure.
Operator will implement BMPs necessary to mitigate a potential for a release of fluids to impact streams, intermittent streams, ditches, and drainage crossings. For these crossings: if poly pipe is used on the surface, operator will ensure appropriate containment by either installing over-sized pipe “sleeves” which extend the length of the crossing and beyond to a distance deemed adequate to capture (catchment basins) and/or divert any possible release of fluids and prevent fluids from reaching the stream or drainage; installing over-sized pipe “sleeves” which extend the length of the crossing and installing shut off valves on either side of crossing instead of catchment basins; or develop an alternative means for containment. For all other pipeline materials, operator will implement BMPs necessary to mitigate a potential for E&P fluids not to reach groundwater or flowing surface water.
Operator will utilize, to the extent practical, all existing access and other public roads, and/or existing pipeline right-of-ways, when placing/routing the temporary surface pipelines. This will reduce surface disturbance and fragmentation of wildlife habitat in the area. |
| OGLA | Form: (02A) 401189822 05/04/2017 | The moisture content of water/bentonite based mud (WBM) generated drill cuttings managed onsite shall be kept as low as practicable to prevent accumulation of liquids greater than de minimis amounts. After drilling and completion operations have been completed, the WBM drill cuttings that will remain on the well pad location (cuttings management area, the cut portion of the pad, cuttings trench, dry cuttings drilling pit), must meet the applicable standards of Table 910-1. No liners are allowed to be disposed of with the drill cuttings. After the drill cuttings have been amended (if necessary) and placed on the well pad, sampling frequency of the drill cuttings (to be determined by the operator) shall be representative of the material left on location. No offsite disposal of cuttings to another oil and gas location shall occur without prior approval of a Waste Management Plan (submitted via a Form 4 Sundry Notice) specifying disposal location and waste characterization method. Commercial disposal of drill cuttings will only require notification to COGCC via a Form 4 Sundry Notice.
Flowback and stimulation fluids must be sent to enclosed tanks, separators, or other containment/filtering equipment before the fluids can be placed into any pipeline storage vessel, or other open top containment located on the well pad; or into tanker trucks for offsite disposal. No open top tanks can be used for initial flowback fluids containment. The flowback and stimulation fluid tanks, separators, or other containment/filtering equipment must be placed on the well pad in an area constructed to be sufficiently impervious to contain any spilled or released material. No additional downgradient berming is required if operator constructs a sufficiently sized perimeter berm.
Potential odors associated with the completions process and/or with long term production operations must be controlled/mitigated. |
| OGLA | Form: (02A) 401189822 05/04/2017 | Operator must ensure secondary containment for any volume of fluids contained at the water storage facility site during operations (as shown on the Construction Layout Drawings attachment); including, but not limited to, construction of a berm or diversion dike, diversion/collection trenches within and/or outside of berms/dikes, site grading, or other comparable measures (i.e., best management practices [BMPs] associated with fluid containment/control as well as stormwater management for the control of run-on and run-off) sufficiently protective of nearby surface water. Any berm constructed at the water storage facility site will be stabilized, inspected at regular intervals as required by CDPHE (at least every 14 days and after precipitation events), and maintained in good condition.
The design/build of any perimeter berm or fluid management structures shall be sized, constructed, and compacted sufficiently to contain and/or manage potential fluid releases during operations in a manner that prevents or controls potential sedimentation and scouring on adjacent lands and drainages. Such design/build of perimeter berms or fluid management structures may include, but are not limited to the following: on location berms; diversion ditches; down gradient baffles intended to slow and control water flow and sediment; enhanced vegetation; or other design features necessary to achieve the goal of protecting adjacent lands and drainages from potential sedimentation and scouring.
The access road will be maintained as to not allow sediment to migrate from the access road to nearby surface water or any drainages leading to surface water.
Strategically apply fugitive dust control measures, including encouraging established speed limits on private roads, to reduce fugitive dust and coating of vegetation and deposition in water sources.
Berms or other containment devices shall be constructed to be sufficiently impervious (corrugated steel with poly liner) to contain any spilled or released material around permanent produced water storage tanks. |
| OGLA | Form: (02A) 401189822 05/04/2017 | In addition to the notifications required by COGCC listed in the Northwest Notification Policy (Notice of Intent to construct a new location, Notice of Intent to spud surface casing, and Notice of Intent to commence hydraulic fracturing operations) and Rule 316C. COGCC Form 42. FIELD OPERATIONS NOTICE (a. Notice of Intent to Conduct Hydraulic Fracturing Treatment; b. Notice of Spud; and c. Notice of Construction or Major Change); operator shall notify the COGCC 48 hours prior to pipeline testing (flowlines from wellheads to separators to tanks; and/or any temporary surface lines used for hydraulic stimulation and/or flowback operations) using the Form 42 (as described in Rule 316C.m. Notice of Completion of Form 2/2A Permit Conditions). The appropriate COGCC individuals will automatically be email notified. |