| Engineer | Form: (04) 400951218 02/19/2016 | 1) This approval grants an extension to the Corrective Action deadline cited on COGCC Field Inspection Report #673402738 (2 circulation pumps and UIC pump are closer to wellhead than required setback distance, comply with 600 series setback rules by 4/10/2016). The new Corrective Action deadline is 8/31/2016.
2) Operator shall contact COGCC OGLA staff to determine reporting requirements, if any, for changes to exisitng equipment on location. |
| | Form: (04) 401590362 03/29/2018 | This Form will not be processed until an amended Form 2A has been approved.
|
| Environmental | Form: (04) 401590362 04/06/2018 | At the conclusion of the pilot test (August 2018), provide a status update regarding the successfulness of the DAF treatment. Include the volume of fluids processed and volume of solids (including filter socks) generated and disposed of at approved facilities. |
| Agency | Form: (02A) 401581277 06/22/2018 | Operator shall pressure test pipelines (inflow and outflow pipelines) in accordance with Rule 1101.e.(1) prior to putting into initial service any temporary surface or permanent buried pipelines and following any reconfiguration of the pipeline network. |
| Agency | Form: (02A) 401581277 06/22/2018 | Potential odors associated with the DAF Unit process and/or with short term operations must be controlled/mitigated. |
| OGLA | Form: (02A) 401581277 06/22/2018 | The access road will be maintained as to not allow any sediment to migrate from the access road to nearby surface water or any drainages leading to surface water.
Strategically apply fugitive dust control measures to reduce fugitive dust and coating of vegetation and deposition in water sources. Operator shall employ practices for control of fugitive dust caused by other operations, including, but not limited to the use of speed restrictions, regular road maintenance, restriction of construction activity during high wind days. Additional management practices such as road surfacing, wind breaks and barriers may be used. |
| OGLA | Form: (02A) 401581277 06/22/2018 | In addition to the notifications required by COGCC listed in Rule 316C. COGCC Form 42. FIELD OPERATIONS NOTICE (c. Notice of Construction or Major Change); operator shall notify the COGCC 48 hours prior to DAF Unit startup and pipeline testing (inflow and outflow pipelines) using the Form 42 (as described in Rule 316C.m. Notice of Completion of Form 2/2A Permit Conditions). The appropriate COGCC individuals will automatically be email notified. |
| Environmental | Form: (04) 402193538 10/04/2019 | Any spills of materials outside of the shale bin shale be reported on a F19. |
| Environmental | Form: (04) 402193538 10/04/2019 | Placement and use of the temporary shale bin through June 4, 2020 is approved. |
| Environmental | Form: (04) 402193538 10/04/2019 | The moisture content of any material placed in the temporary shale bin shall be as low as practicable to prevent accumulation of liquids greater than de minimis amounts. Any accumulation of liquids shall be removed upon discovery and immediately disposed of at an approved facility. |
| Environmental | Form: (04) 402193538 10/04/2019 | The Operator shall keep records of the type(s), volume, origin, and final disposition of E&P waste transferred to the the temporary shale bin. These shale be reported in the annual report for the CE&P Facility. |
| Environmental | Form: (04) 402193538 10/04/2019 | Within 45-days of this Sundry approval, provide a detailed site diagram of the placement of the temporary shale bin. |
| Environmental | Form: (04) 402193538 10/04/2019 | The placement of the temporary shale bin shall be secured to prevent non-authorized placement of material(s) in the bin. |
| Environmental | Form: (04) 402235367 07/08/2020 | Per doc number 402193538, “Placement and use of the temporary shale bin through June 4, 2020 is approved.” If the bin is still on location, please submit a sundry with status of bin. |
| OGLA | Form: (04) 403166142 09/19/2022 | Operator will submit a scaled facility layout drawing within 60 days of construction. |