Engineer | Form: (02 ) 402099155 5/22/2020 | 1) Submit Form 42 electronically to COGCC 48 hours prior to MIRU (spud notice) for the first well activity with a rig on the pad and provide 48 hour spud notice via Form 42 for all subsequent wells drilled on the pad.
2) Comply with Rule 317.j. and provide cement coverage from TD to a minimum of 200' above Niobrara. Verify coverage with cement bond log.
3) Oil-based drilling fluid is to be used only after all fresh water aquifers are covered. |
Engineer | Form: (02 ) 402099155 5/22/2020 | Operator acknowledges the proximity of the non-operated listed well. Operator agrees to: provide mitigation option 1 or 2 (per the DJ Basin Horizontal Offset Policy) to mitigate the situation, ensure all applicable documentation is submitted based on the selected mitigation option chosen, and submit a Form 42 (“OFFSET MITIGATION COMPLETED”) stating that appropriate mitigation occurred and that it has been completed, prior to the hydraulic stimulation of this well.
05-123-13340, MARGUERITE B LEHL A-1 |
Engineer | Form: (02 ) 402099155 5/22/2020 | Operator acknowledges the proximity of the listed non-operated wells. Operator assures that this offset list will be remediated per the DJ Basin Horizontal Offset Policy (option 3). Operator will submit a Form 42 (“OFFSET MITIGATION COMPLETED”) stating what appropriate mitigation occurred and that it has been completed, prior to the hydraulic stimulation of this well.
123-15312, DREYER 32-1
123-14807, SAWYER/POWELL 32-4
001-09250, HSR-MILE HIGH 6-6
001-06702, ADAM TEN LTD 1 |
Engineer | Form: (02 ) 402099155 5/22/2020 | Per COGCC Order 1-232, Bradenhead tests shall be performed according to the following schedule and Form 17 submitted within 10 days of each test:
1) Within 60 days of rig release, prior to stimulation. If any pressure greater than 200 psi, must contact COGCC engineer prior to stimulation.
2) If a delayed completion, 6 months after rig release and prior to stimulation. If any pressure greater than 200 psi, must contact COGCC engineer prior to stimulation.
3) A post-production test within 60 days after first sales, as reported on the Form 10, Certificate of Clearance. |
Engineer | Form: (02 ) 402099155 7/20/2020 | Operator acknowledges the proximity of the listed non-operated well. Operator assures that this offset well will be remediated per the DJ Basin Horizontal Offset Policy (option 4). Operator will submit a Form 42 (“OTHER- AS SPECIFIED BY PERMIT CONDITION”) stating that appropriate mitigation will be completed, during the hydraulic stimulation of this well.
05-123-07782, SACK-HIETT 1 (operator will not complete County Line 3130-06H within 1500’ of this well - estimated between 1280’ FSL and 680’ FSL based on preliminary trajectory) |
Permit | Form: (02 ) 402099155 7/27/2020 | This Permit to Drill is approved subject to all the BMPs and COAs on the most recently approved Form 2A and any subsequently approved Form 4 for the Oil and Gas Location (Location ID 474767). The most recently approved Form 2A and any subsequent Form 4s containing applicable COAs for this location shall be posted onsite during construction, drilling, and completions operations. |
Permit | Form: (02 ) 402099155 7/27/2020 | If the location has not been built by the Form 2A (Doc #402092786) expiration date of 04/01/2023, Operator must Refile the Form 2A for approval prior to location construction.
|
Permit | Form: (04 ) 402680080 5/19/2021 | Operator will ensure the wellbore beyond the unit boundary setback is physically isolated and is not completed. In the Operator Comments on the Form 5A the operator will (1) report the footages from the section lines of the bottom of the completed interval (2) describe how the wellbore beyond the unit boundary setback is physically isolated and (3) certify that none of the wellbore beyond the setback was completed. |
Engineer | Form: (04 ) 402680080 6/9/2021 | Comply with Rule 408.j. and provide cement coverage from TD to a minimum of 500' above Niobrara. Verify coverage with cement bond log.
|