| Engineer | Form: (02) 401508420 02/09/2018 | 1) Submit Form 42 electronically to COGCC 48 hours prior to MIRU (spud notice) for the first well activity with a rig on the pad and provide 48 hour spud notice via Form 42 for all subsequent wells drilled on the pad.
2) Provide cement coverage to a minimum of 200' above Niobrara. Verify coverage with cement bond log.
3) Oil-based drilling fluid is to be used only after setting surface casing.
Bradenhead tests shall be performed and reported according to the following schedule
and Form 17 submitted within 10 days of each test.:
1) All: Within 60 days of rig release, prior to stimulation.
2) Delayed completion: 6 months after rig release, prior to stimulation.
3) All: Within 30 days of first production, as reported on Form 5A.
|
| Permit | Form: (02) 401508420 01/14/2019 | Operator will insure the wellbore beyond the unit boundary setback is physically isolated and is not completed. In the Operator Comments on the Form 5A the operator will (1) report the footages from the section lines of the bottom of the completed interval (2) describe how the wellbore beyond the unit boundary setback is physically isolated and (3) certify that none of the wellbore beyond the setback was completed. |
| Engineer | Form: (04) 402381749 09/14/2020 | 1) Surface casing depth and cement quantity will remain as permitted on the approved APD.
2) This approved sundry includes changes to the approved APD for this well and will be displayed along with the approved APD at the rig while drilling.
3) The Operator will abide by the COGCC Policy for Bradenhead Monitoring During Hydraulic Fracturing Treatments in the Greater Wattenberg Area, May 29, 2012. |
| Permit | Form: (02) 402687409 06/14/2021 | Operator will ensure the wellbore beyond the unit boundary setback is physically isolated and is not completed. In the Operator Comments on the Form 5A the operator will (1) report the footages from the section lines of the bottom of the completed interval (2) describe how the wellbore beyond the unit boundary setback is physically isolated and (3) certify that none of the wellbore beyond the setback was completed. |
| Permit | Form: (02) 402687409 06/15/2021 | If the location has not been built by the Form 2A (Doc #401507549) expiration date of 01/24/2022, Operator must apply for an OGDP and submit a Refile Form 2A for approval prior to location construction. |
| Engineer | Form: (02) 402687409 07/06/2021 | Per COGCC Order 1-232, Bradenhead tests shall be performed according to the following schedule and Form 17 submitted within 10 days of each test:
1) Within 60 days of rig release, prior to stimulation. If any pressure greater than 200 psi, must contact COGCC engineer prior to stimulation.
2) If a delayed completion, 6 months after rig release and prior to stimulation. If any pressure greater than 200 psi, must contact COGCC engineer prior to stimulation.
3) A post-production test within 60 days after first sales, as reported on the Form 10, Certificate of Clearance. |
| Engineer | Form: (02) 402687409 07/06/2021 | 1) Submit Form 42 electronically to COGCC 48 hours prior to MIRU (spud notice) for the first well activity with a rig on the pad and provide 48 hour spud notice via Form 42 for all subsequent wells drilled on the pad.
2) Provide cement coverage from TD to a minimum of 500' above Niobrara. Verify coverage with cement bond log. Confirm rule and cement coverage with COGCC Area Engineer prior to drilling this well.
3) Oil-based drilling fluid is to be used only after all fresh water aquifers are covered.
4) The Operator will abide by the COGCC Policy for Bradenhead Monitoring During Hydraulic Fracturing Treatments in the Greater Wattenberg Area, May 29, 2012. |
| Permit | Form: (04) 403114023 08/10/2022 | COGCC COA: Operator will ensure the wellbore beyond the unit boundary setback is physically isolated and is not completed. In the Operator Comments on the Form 5A the operator will (1) report the footages from the section lines of the bottom of the completed interval (2) describe how the wellbore beyond the unit boundary setback is physically isolated and (3) certify that none of the wellbore beyond the setback was completed. |
| Engineer | Form: (04) 403114023 08/15/2022 | Approval of this sundry makes changes to the approved APD and a copy of this sundry shall be displayed along with the APD in the doghouse while this well is being drilled. |