| Engineer | Form: (02) 401539455 03/26/2018 | 1) Submit Form 42 electronically to COGCC 48 hours prior to MIRU (Spud Notice), for the first well/activity on the pad and provide 48 hour spud notice for all subsequent wells drilled on the pad.
2) Comply with Rule 317.j and provide cement coverage from the end of production casing to a minimum of 200' above Niobrara. Verify coverage with cement bond log.
|
| Engineer | Form: (02) 401539455 03/26/2018 | Bradenhead tests shall be performed and reported according to the following schedule and Form 17 submitted within 10 days of each test:
1) Within 60 days of rig release and prior to stimulation or
2) If a delayed completion, 6-7 months after rig release and prior to stimulation.
3) Within 30 days after first production, as reported on Form 5A.
|
| Engineer | Form: (04) 402506452 11/05/2020 | This well may return to annual testing. If at any point in the future well conditions meet thresholds defined by Order 1-232 a new bradenhead sundry must be submitted. |