| Engineer | Form: (02) 401410737 11/08/2017 | Operator acknowledges the proximity of the listed offset well(s). Operator agrees to comply with the DJ Basin Horizontal Offset Policy to mitigate the situation, ensure all applicable documentation is submitted based on the selected mitigation option chosen, submit Form 42(s) (“OFFSET MITIGATION COMPLETED”) for the mitigated well(s), stating that appropriate mitigation was completed prior to the hydraulic stimulation of this well.
Offset wells to mitigate:
05-123-07358, RADER-FEDERAL 1, Option 3
05-123-19211, THOMAS D, Option 3
|
| Engineer | Form: (02) 401410737 11/08/2017 | 1) Submit Form 42 electronically to COGCC 48 hours prior to MIRU (spud notice) for the first well activity with a rig on the pad and provide 48 hour spud notice via Form 42 for all subsequent wells drilled on the pad.
2) Provide cement coverage to a minimum of 200' above Niobrara. Verify coverage with cement bond log.
3) Oil-based drilling fluid is to be used only after setting surface casing. |
| Engineer | Form: (02) 401410737 11/08/2017 | Bradenhead tests shall be performed and reported according to the following schedule
and Form 17 submitted within 10 days of each test.:
1) All: Within 60 days of rig release, prior to stimulation.
2) Delayed completion: 6 months after rig release, prior to stimulation.
3) All: Within 30 days of first production, as reported on Form 5A.
|
| Permit | Form: (02) 401410737 04/11/2018 | The proposed bottom hole footage is inside the unit setback. Therefore, operator shall provide in a comment on the Form 5A, Completed Interval Report - Submit tab, a certification that the bottom of the completed interval is legal with respect to the unit setback, and will provide the following information: 1) the measured depth of the bottom perforation and its distance from the unit boundary, 2) the measured depth of the float collar or other device, that ensures that the well is not perforated inside the unit setback.
|