COGIS - Conditions of Approval Results
TypeSource DocumentConditions of Approval
EngineerForm: (02)
401455500
02/14/2018
Bradenhead tests shall be performed according to the following schedule and the Form 17 submitted within 10 days of each test: 1) Within 60 days of rig release and prior to stimulation and 2) If a delayed completion, 6 months after rig release and prior to stimulation. 3) Within 30 days after first production, as reported on Form 5A.
EngineerForm: (02)
401455500
02/14/2018
1) Submit Form 42 electronically to COGCC 48 hours prior to MIRU (spud notice) for the first well activity with a rig on the pad and provide 48 hour spud notice via Form 42 for all subsequent wells drilled on the pad. 2) Comply with Rule 317.j. and provide cement coverage from TD to a minimum of 200' above Niobrara. Verify coverage with cement bond log. 3) Oil-based drilling fluid is to be used only after all fresh water aquifers are covered.
EngineerForm: (02)
401455500
02/14/2018
Operator acknowledges the proximity of the non-operated listed well. Operator agrees to: provide mitigation option 1 or 2 (per the DJ Basin Horizontal Offset Policy) to mitigate the situation, ensure all applicable documentation is submitted based on the selected mitigation option chosen, and submit a Form 42 (“OFFSET MITIGATION COMPLETED”) stating that appropriate mitigation occurred and that it has been completed, prior to the hydraulic stimulation of this well. 05-123-13749, UPRR-RICKETSON 1
OGLAForm: (04)
403096385
07/19/2022
Operator will implement measures to capture, combust, or control emissions to protect health and safety, and to ensure that vapors and odors from well completion(s), well repair/maintenance, well perforating, temporary abandonment activities, additional equipment installation, and/or testing operations with a workover rig, wireline rig, or other heavy equipment do not constitute a nuisance or hazard to public health, welfare and the environment. Due to proximity of building units (BUs) all blowdown gases will be controlled.
 
COGIS - Best Management Practice Results
BMP TypeSource DocumentBest Management Practices
Drilling/Completion OperationsForm: (02 )
401455500
2/15/2018
Kerr-McGee acknowledges and will comply with the COGCC Policy for Bradenhead Monitoring during Hydraulic Fracturing Treatments in the Greater Wattenberg Area dated May 29, 2012.
Drilling/Completion OperationsForm: (02 )
401455500
2/15/2018
Anti-Collision: Kerr-McGee will perform an anti-collision evaluation of all active (producing, shut in, or temporarily abandoned) offset wellbores that have the potential of being within one hundred fifty (150) feet of a proposed well prior to drilling operations for the proposed well. Notice shall be given to all offset operators within one hundred fifty (150) feet prior to drilling.
Drilling/Completion OperationsForm: (02 )
401455500
2/15/2018
317.p Logging Program: One of the first wells drilled on the pad will be logged with Cased-hole Pulsed Neutron Log with Gamma Ray Log the kick-off point into the surface casing. All wells on the pad will have a cement bond log with gamma-ray run on production casing (or on intermediate casing if production liner is run) into the surface casing. The horizontal portion of every well will be logged with a measured-while-drilling gamma-ray log. The Form 5, Completion Report, for each well on the pad will list all logs run in that well and have those logs attached. The Form 5 for each well shall clearly state “No open-hole logs were run” and shall reference the Rule 317.p Exception granted for the well.
PlanningForm: (04 )
403096385
8/1/2022
Operations are daylight-only; no lighting impacts are anticipated from operations. IF 24HR RIG: Site lighting will be shielded and directed downward and inward toward operations to avoid glare on public roads and nearby Building Units.
Community Outreach and NotificationForm: (04 )
403096385
8/1/2022
Signs will be placed in conspicuous locations and will include Oxy contact information; the Oxy Stakeholder Relations team will respond to all community member inquiries. The signs will be placed so as not to create a potential traffic hazard
Community Outreach and NotificationForm: (04 )
403096385
8/1/2022
Courtesy notifications will be sent to all parcel owners with building units within 1,500 feet of the location letting them know about our subsequent well operations and providing contact information for Kerr McGee’s response line and online resources.
WildlifeForm: (04 )
403096385
8/1/2022
This location was identified to be within a historical raptor nest buffer. If this operation is planned between 2/15 – 7/31, a field survey to determine the status of the nest will be required approximately 2 weeks prior to the start of operations. If the nest is determined to be active and work cannot be delayed, HSE will consult with CPW prior to operations beginning.
Dust controlForm: (04 )
403096385
8/1/2022
Water will be placed on dirt access roads to mitigate dust as needed.
Noise mitigationForm: (04 )
403096385
8/1/2022
Operations will be in compliance with Table 423-1 requirements. Based off the rig sound signature, rig orientation will be considered to reduce noise levels to nearby building units. IF 24HR RIG: Noise associated with pipe handling, traffic, and other operational activity will be minimized between 7:00 pm and 7:00 am. Based off the rig sound signature, rig orientation will be considered to reduce noise levels to nearby building units.
Odor mitigationForm: (04 )
403096385
8/1/2022
Closed, upright tanks are being utilized to mitigate odor.
PlanningForm: (04 )
403392466
6/12/2023
Site lighting will be shielded and directed downward and inward toward operations to avoid glare on public roads and nearby Building Units.
Community Outreach and NotificationForm: (04 )
403392466
6/12/2023
Signs will be placed in conspicuous locations and will include Oxy contact information; the Oxy Stakeholder Relations team will respond to all community member inquiries. The signs will be placed so as not to create a potential traffic hazard
Community Outreach and NotificationForm: (04 )
403392466
6/12/2023
Courtesy notifications will be sent to all parcel owners with building units within 2,000 feet of the location letting them know about our subsequent well operations and providing contact information for Kerr McGee’s response line and online resources.
WildlifeForm: (04 )
403392466
6/12/2023
Between 12/1 through 4/30, KMOG will only perform rig operations during daylight hours, Monday through Friday. KMOG access roads have speed limit restrictions that all personnel will follow. KMOG will shut down operations if an extreme winter storm is anticipated.
Dust controlForm: (04 )
403392466
6/12/2023
Water will be placed on dirt access roads to mitigate dust as needed.
Noise mitigationForm: (04 )
403392466
6/12/2023
Noise associated with pipe handling, traffic, and other operational activity will be minimized between 7:00 pm and 7:00 am. Based off the rig sound signature, rig orientation will be considered to reduce noise levels to nearby building units.