Engineer | Form: (02 ) 401198397 8/4/2017 | 1) Submit Form 42 electronically to COGCC 48 hours prior to MIRU (Spud Notice), for the first well/activity on the pad and provide 48 hour spud notice for all subsequent wells drilled on the pad.
2) Comply with Rule 317.j and provide cement coverage from the end of production casing to a minimum of 200' above Niobrara. Verify coverage with cement bond log.
|
Engineer | Form: (02 ) 401198397 8/4/2017 | Bradenhead tests shall be performed and reported according to the following schedule and Form 17 submitted within 10 days of each test:
1) Within 60 days of rig release and prior to stimulation or
2) If a delayed completion, 6-7 months after rig release and prior to stimulation.
3) Within 30 days after first production, as reported on Form 5A.
|
Engineer | Form: (04 ) 401963538 3/27/2019 | 1) Operator shall implement measures to control venting, to protect health and safety, and to ensure that vapors and odors from well operations do not constitute a nuisance or hazard to public welfare.
2) At the conclusion of the cycles, submit a Sundry that summarizes current well condition and includes the flow rate information and pressure data. |
Engineer | Form: (04 ) 402262843 12/26/2019 | Conduct a new bradenhead test and submit the Form 17 within ten days of the test to demonstrate compliance with Order 1-232 and current wellbore conditions. |