| Engineer | Form: (02) 401217957 05/05/2017 | Operator agrees to comply with the DJ Basin Horizontal Offset Policy to mitigate the situation, ensure all applicable documentation is submitted based on the selected mitigation option chosen, submit Form 42(s) (“OFFSET MITIGATION COMPLETED”) for the remediated well(s), referencing the API Number of the proposed horizontal well, to report that appropriate mitigation was completed prior to the hydraulic stimulation of the proposed horizontal well.
Operator acknowledges the proximity of the following offset well(s) of concern:
05-123-11852, CARLETON 1
05-123-11988, JONES 1
|
| Engineer | Form: (02) 401217957 05/05/2017 | 1) Submit Form 42 electronically to COGCC 48 hours prior to MIRU (spud notice) for the first well activity with a rig on the pad and provide 48 hour spud notice via Form 42 for all subsequent wells drilled on the pad.
2) Provide cement coverage to a minimum of 200' above Niobrara. Verify coverage with cement bond log.
|
| Engineer | Form: (02) 401217957 05/05/2017 | Bradenhead tests shall be performed and reported according to the following schedule
and Form 17 submitted within 10 days of each test.:
1) All: Within 60 days of rig release, prior to stimulation.
2) Delayed completion: 6 months after rig release, prior to stimulation.
3) All: Within 30 days of first production, as reported on Form 5A.
|
| Engineer | Form: (02) 403037117 07/25/2022 | 1) Submit Form 42 electronically to COGCC 2 business days prior to MIRU (Spud Notice), for the first well/activity on the pad and provide 2 business days spud notice for all subsequent wells drilled on the pad.
2) Comply with Rule 408.j and provide cement coverage from the end of production casing to a minimum of 500' above Niobrara. Verify coverage with cement bond log.
3) Oil-based drilling fluid is to be used only after all aquifers are covered. |
| Engineer | Form: (02) 403037117 07/25/2022 | Per COGCC Order 1-232, Bradenhead tests shall be performed according to the following schedule and Form 17 submitted within 10 days of each test:
1) Within 60 days of rig release, prior to stimulation. If any pressure greater than 200 psi, must contact COGCC engineer prior to stimulation.
2) If a delayed completion, a second test is required between 6-9 months, of if there is pressure above 200 psi, after rig release and prior to stimulation. If any pressure greater than 200 psi, must contact COGCC engineer prior to stimulation.
3) A post-production test within 60 days after first sales, as reported on the Form 10, Certificate of Clearance. |
| Permit | Form: (02) 403037117 07/29/2022 | RETURNED TO DRAFT: This application has been reviewed by COGCC staff and cannot be approved based on the information submitted; therefore, the COGCC is returning this form to DRAFT for the applicant to resolve the issues. In compliance with § 24-65.1-108(1), C.R.S., the COGCC is returning this application to the applicant to remedy the deficiencies. The applicant may resubmit this application for COGCC review; upon resubmittal of any application, the COGCC will have 60 days in which to approve, deny, or request all additional information necessary to complete the regulatory review.
In addition to all standard required information and attachments, the COGCC hereby confirms the following information is necessary for review:
1.Well type
2.Field name
3.Spacing order
4.Refile comment
5.Open Hole BMP.
|
| Permit | Form: (02) 403037117 09/13/2022 | If conductors are preset, operator shall comply with Notice to Operators: Procedures for Preset Conductors (dated September 1, 2016).
|
| Permit | Form: (02) 403037117 09/13/2022 | Operator shall comply with Notice to Operators: Interim Reclamation Procedures for Delayed Operations (dated January 5, 2017).
|