Engineer | Form: (02 ) 401162599 2/7/2017 | Operator acknowledges the proximity of the listed non-operated well. Operator assures that this offset list will be remediated per the DJ Basin Horizontal Offset Policy (option 3). Operator will submit a Form 42 (“OFFSET MITIGATION COMPLETED”) stating what appropriate mitigation occurred and that it has been completed, prior to the hydraulic stimulation of this well.
05-123-07592, CLARA A BACON 1 |
Engineer | Form: (02 ) 401162599 2/7/2017 | Bradenhead tests shall be performed according to the following schedule and the Form 17 submitted within 10 days of each test:
1) Within 60 days of rig release and prior to stimulation and
2) If a delayed completion, 6 months after rig release and prior to stimulation.
3) Within 30 days after first production, as reported on Form 5A. |
Engineer | Form: (02 ) 401162599 2/7/2017 | 1) Submit Form 42 electronically to COGCC 48 hours prior to MIRU (spud notice) for the first well activity with a rig on the pad and provide 48 hour spud notice via Form 42 for all subsequent wells drilled on the pad.
2) Comply with Rule 317.j. and provide cement coverage from TD to a minimum of 200' above Niobrara. Verify coverage with cement bond log. |
Engineer | Form: (04 ) 401319917 6/29/2017 | This Form 4 makes changes to the approved Form 2 and must be displayed with the Form 2 while drilling.
1) Submit Form 42 electronically to COGCC 48 hours prior to MIRU (spud notice) for the first well activity with a rig on the pad and provide 48 hour spud notice via Form 42 for all subsequent wells drilled on the pad.
2) Comply with Rule 317.j. and provide cement coverage from end of 7-inch casing to a minimum of 200' above Niobrara. Verify coverage with cement bond log. |
Engineer | Form: (04 ) 401425081 10/17/2017 | 1) Submit Form 42 electronically to COGCC 48 hours prior to MIRU (spud notice) for the first well activity with a rig on the pad and provide 48 hour spud notice via Form 42 for all subsequent wells drilled on the pad.
2) Comply with Rule 317.j. and provide cement coverage from end of 7-inch casing to a minimum of 200' above Niobrara. Verify coverage with cement bond log.
3) Oil-based drilling fluid is to be used only after all fresh water aquifers are covered. |
Engineer | Form: (04 ) 401660618 6/19/2018 | Operator must submit a Sundry no later than July 6, 2018, that summarizes the investigation and identifies the cause of the bradenhead pressure spike.
|
Engineer | Form: (04 ) 402151283 9/26/2019 | 1. Operator shall implement measures to control venting, to protect health and safety, and to ensure that vapors and odors from well operations do not constitute a nuisance or hazard to public welfare.
2. Prior to starting bradenhead abatement, if a sample has not been collected within the last twelve months collect bradenhead and production gas samples for laboratory analysis. Sampling shall comply with Operator Guidance - Bradenhead Testing and Reporting Instructions, Appendix A: Liquid and Gas Sampling. Copies of all final laboratory analytical results shall be provided to the COGCC within three months of collecting the samples.
3. Bradenhead gas is not to be vented to atmosphere; any gas from the Bradenhead will be routed to an enclosed tank and/or combustor. Operator shall implement measures to get an initial estimate of the gas flow rate and/or volume from the bradenhead. The abatement program may be used for six consecutive months.
4. Operator will submit a Form 42 (“OTHER”) stating that “bradenhead abatement program has started.”
5. At the conclusion of the six months, conduct a new bradenhead test and submit the Form 17 within ten days of the test and submit a Form 4 Sundry that summarizes current well condition. The sundry should include details of the future plans and the flow rate information and pressure data.
|
Engineer | Form: (04 ) 402151283 9/26/2019 | Shut in bradenhead pressure shall not exceed 50 psig.
|
Engineer | Form: (04 ) 402561426 12/30/2020 | Operator shall continue to monitor pressure, and report to COGCC through annual testing. If monitored well conditions meet the thresholds defined by Order 1-232 a new bradenhead sundry must be filed.
|
Engineer | Form: (04 ) 403925385 9/24/2024 | 1) Provide electronic Form 42-Other ("Treatment") two business days ahead of operations.
2) During treatment operations, the operator will continuously monitor the surface and casing pressures of the wellbore being treated. If there is any reason to suspect a potential downhole failure during treatment operations, stop treatment and contact ECMC engineering.
3) The Operator will submit the Form 5A, Completed Interval Report within 30 days after the treatment operations
4) If treatment includes the use of a rig, Per RUle 408.m, conducta successful pressure test prior to stimulation. |