Skip to Main Content

COGIS DB

 
Facility TypeFacility ID/
API
Facility Name/
Number
Operator Name/
Number
StatusField Name/
Number
LocationLocation IDRelated Facilities
WELL05-123-36846USA FED
28N-36HZ
KERR MCGEE OIL & GAS ONSHORE LP
47120
PR
10/1/2018
WATTENBERG
90750
WELD  123
SESW 36 3N66W 6
336306View Related
 
COGIS - Conditions of Approval Results
TypeSource DocumentConditions of Approval
EngineerForm: (02 )
400367420
1/28/2013
1)Note surface casing setting depth change from 800’ to 840’. Increase cement coverage accordingly and cement to surface. 2)Provide notice of MIRU via an electronic Form 42. 3)Comply with Rule 317.i and provide cement coverage to a minimum of 200' above the Niobrara. Verify cement coverage with a cement bond log per 317.o.
 
COGIS - Best Management Practice Results
BMP TypeSource DocumentBest Management Practices
Drilling/Completion OperationsForm: (02 )
400367420
2/22/2013
“Prior to drilling operations, Operator may perform an anti-collision review of existing offset wells that have the potential of being within close proximity of the proposed well. This anti-collision review may include MWD or gyro surveys and surface locations of the offset wells with included error of uncertainty per survey instrument, and compared against the proposed wellpath with its respective error of uncertainty. If current surveys do not exist for the offset wells, Operator may have gyro surveys conducted to verify bottomhole location. The proposed well may only be drilled if the anti-collision review results indicate that the risk of collision is sufficiently low as defined by the anti-collision plan, with separation factors greater than 1.5, or if the risk of collision has been mitigated through other means including shutting in wells, plugging wells, increased drilling fluid in the event of lost returns or as is appropriate for the specific situation. In the event of an increased risk of collision, that risk will be mitigated to prevent harm to people, the environment or property. For the proposed well, upon conclusion of drilling operations, an as-constructed directional survey will be submitted to COGCC with the Form 5.” At the time of permitting, the operator has identified the following well(s) as being within close proximity of the proposed well: HSR-Federal 14-36
Drilling/Completion OperationsForm: (02 )
400367420
2/22/2013
Kerr McGee acknowledges and will comply with the COGCC Policy for Bradenhead Monitoring during Hydraulic Fracturing Treatments in the Greater Wattenberg Area dated May 29, 2012.