COGIS - Conditions of Approval Results
TypeSource DocumentConditions of Approval
EngineerForm: (02 )
400325434
9/18/2012
1)Provide notice of MIRU via an electronic Form 42. 2)Comply with Rule 317.i and provide cement coverage from the 7” casing TD to a minimum of 200' above the Niobrara and from 200’ below Sussex to 200’ above Sussex. Verify coverage with a cement bond log.
PermitForm: (02 )
400325434
9/20/2012
Operator must meet water well testing requirements per Rule 318A.
 
COGIS - Best Management Practice Results
BMP TypeSource DocumentBest Management Practices
Drilling/Completion OperationsForm: (02 )
400325434
10/4/2012
Prior to drilling operations, Operator may perform an anti-collision review of existing offset wells that have the potential of being within close proximity of the proposed well. This anti-collision review may include MWD or gyro surveys and surface locations of the offset wells with included error of uncertainty per survey instrument, and compared against the proposed wellpath with its respective error of uncertainty. If current surveys do not exist for the offset wells, Operator may have gyro surveys conducted to verify bottomhole location. The proposed well may only be drilled if the anti-collision review results indicate that the risk of collision is sufficiently low as defined by the anti-collision plan, with separation factors greater than 1.5, or if the risk of collision has been mitigated through other means including shutting in wells, plugging wells, increased drilling fluid in the event of lost returns or as is appropriate for the specific situation. In the event of an increased risk of collision, that risk will be mitigated to prevent harm to people, the environment or property. For the proposed well, upon conclusion of drilling operations, an as-constructed directional survey will be submitted to COGCC with the Form 5.” At the time of permitting; the operator has identified the following well(s) as being within close proximity of the proposed well: REIGLE 3C-4HZ: - REIGLE 18-4 - REIGLE 22-4 - HAYMAKER 35N-4HZ
Drilling/Completion OperationsForm: (02 )
400325434
10/4/2012
Kerr McGee acknowledges and will comply with the COGCC Policy for Bradenhead Monitoring during Hydraulic Fracturing Treatments in the Greater Wattenberg Area dated May 29, 2012.