| Drilling/Completion Operations | Form: (02 ) 400196317 9/30/2011 | 1 -- During the fracing of this Clark horizontal well, Kerr-McGee will monitor the bradenhead pressure of the existing UPRR 50 PAN AM J1 well that is ~15'-60' from this well.
2. Bradenhead pressure gauges are to be installed 24 hours prior to stimulation. The gauges are to read at least once during every 24-hour period until 24-hours after stimulation is completed (post flowback). The gauges are to be of the type able to read current pressure and record the maximum encountered pressure in a 24-hour period. The gauge is to be reset between each 24-hour period. The pressures are to be recorded and saved.
3. If at any time during stimulation or the 24-hour post-stimulation period, the bradenhead annulus pressure of the treatment well or offset wells increases more than 200 psig, as per Rule 341, the operator of the well being stimulated shall verbally notify the Director as soon as practicable, but no later than twenty-four (24) hours following the incident. Within fifteen (15) days after the occurrence, the operator shall submit a Sundry Notice, Form 4, giving all details, including corrective actions taken.
|
| Drilling/Completion Operations | Form: (02 ) 400196317 9/30/2011 | 2 -- The UPRR 50 Pan Am J#1 will have a Gyroscope survey run on it prior to the drilling of the well to ensure no collision issues.
|