| Engineer | Form: (02) 400134906 03/25/2011 | 1) Provide 24 hour notice of MIRU to Jim Precup at 303-469-1902 or e-mail at james.precup@state.co.us
2) Set at least 980’ of surface casing per Rule 317A, cement to surface.
3) Comply with Rule 317.i and provide cement coverage from TD to a minimum of 200' above Niobrara. Verify coverage with cement bond log.
|
| Engineer | Form: (04) 402066195 07/01/2019 | This approval is good for one year and a new application must be made before June 6, 2018 (1 year from prior application). Updates for the planned utilization of the well should be included with the application. |
| Engineer | Form: (04) 402408548 11/03/2020 | This approval is good for one year and a new application must be made before May 28,2021. Updates for the planned utilization of the well should be included with the application.
|
| Engineer | Form: (04) 402408548 11/03/2020 | The Form 7 reporting must reflect the well status dates reported on the Form 4-TA request.
|
| Engineer | Form: (04) 402758567 07/28/2021 | Operator shall continue to monitor pressure, and report to COGCC through annual testing. If monitored well conditions meet the thresholds defined by Order 1-232 a new bradenhead sundry must be filed.
|
| Engineer | Form: (04) 402896118 12/28/2021 | 1. Operator will implement measures to control venting, to protect health and safety, and to ensure that vapors and odors from well operations do not constitute a nuisance or hazard to public welfare.
2. Well to be plugged by 12/31/2022. Summary of well monitoring and mitigation to be submitted on a Form 4 Sundry after well has been plugged and abandoned. The sundry should include pressure data, flow rate information, sample analysis interpretation, and bradenhead test description.
3. Shut in bradenhead pressure shall not exceed 50 psig. |
| Engineer | Form: (04) 402717205 04/29/2022 | 1) Effective April 30, 2022 this well will be designated inactive and must be properly returned to production, plugged and abandoned, have an approved Form 5B or be added to a Form 6A list no later than November 1, 2022.
|
| Engineer | Form: (06) 403093857 07/27/2022 | Prior to starting plugging operations a bradenhead test shall be performed if there has not been a reported bradenhead test within the 60 days immediately preceding the start of plugging operations.
1) If, before opening the bradenhead valve, the beginning pressure is greater than 25 psi, sampling is required.
2) If pressure remains at the conclusion of the test, or if any liquids were present during the test, sampling is required.
The Form 17 shall be submitted within 10 days of the test. Sampling shall comply with Operator Guidance - Bradenhead Testing and Reporting Instructions. If samples are collected, copies of all final laboratory analytical results shall be provided to the COGCC within three (3) months of collecting the samples.
If there is a need for sampling, contact COGCC engineering for verification of plugging procedure.
|
| Engineer | Form: (06) 403093857 07/27/2022 | Operator shall implement measures to control venting, to protect health and safety, and to ensure that vapors and odors from well plugging operations do not constitute a nuisance or hazard to public welfare.
|
| Engineer | Form: (06) 403093857 07/27/2022 | Consistent with Rule 911.a, a Form 27 must be approved prior to cut and cap, conducting flowline abandonment, or removing production equipment. Allow 30 days for Director review of the Form 27; include the Form 27 document number on the Form 44 for offsite flowline abandonment (if applicable) and on the Form 6 Subsequent.
Properly abandon flowlines per Rule 1105. If flowlines will be abandoned in place, include with the Form 27: pressure test results conducted in the prior 12 months as well as identification of any document numbers for a COGCC Spill/Release Report, Form 19, associated with the abandoned line.
|
| Engineer | Form: (06) 403093857 07/27/2022 | 1) Provide electronic Form 42 Notice of MIRU 2 business days ahead of operations and electronic Form 42 Notice of Plugging Operations 48 hours prior to mobilizing for plugging operations.
2) After placing plug at 2800’ assure that all fluid migration has been eliminated by monitoring the well for a minimum of 8 hours before proceeding to the next plug. If at any time after placing this plug there is evidence of pressure or of fluid migration, contact COGCC engineering before continuing operations.
3) Prior to placing the 1145’ plug: verify that all fluid (liquid and gas) migration has been eliminated. If evidence of fluid migration or pressure remains, contact COGCC Engineer for an update to plugging orders.
4) After isolation has been verified, pump surface casing shoe plug. If cement is not circulated to surface, shut-in, WOC 4 hours then tag plug – must be at 992’ or shallower and provide a minimum of 10 sx plug at the surface.
5) Leave at least 100’ of cement in the wellbore for each plug without mechanical isolation.
6) With the Form 6 SRA operator must provide written documentation which positively affirms each COA listed above has been addressed.
|