Permit | Form: (02 ) 400119053 2/7/2011 | -Operator must meet the water well testing requirements as per Rule 318A.e.(4) |
Engineer | Form: (02 ) 400119053 2/18/2011 | Note surface casing setting depth change from 400’ to 670’. Increase cement coverage accordingly and cement to surface.
1) Provide 24 hr notice of MIRU to Colby Horton at 970-370-0040 or colby.horton@state.co.us.
2) Set surface casing per Rule 317d, cement to surface. Setting surface casing less than the approved depth is a permit violation unless prior written approval is obtained from the COGCC.
3) If completed, provide cement coverage from the intermediate casing shoe to a minimum of 200' above Niobrara. Verify cement with a cement bond log.
4) Comply with Rule 321. Run and submit Directional Survey from TD to base of surface casing. Ensure that the wellbore complies with setback requirements in commission orders or rules prior to producing the well.
|
Permit | Form: (06 ) 402652794 4/15/2021 | Reported "as drilled" GPS data is inaccurate. Submit accurate "as drilled" GPS data on Subsequent Report of Abandonment. GPS data must meet the requirements of Rule 216. |
OGLA | Form: (06 ) 402652794 4/21/2021 | Operator will implement measures to capture, combust, or control emissions to protect health and safety, and to ensure that vapors and odors from well plugging operations do not constitute a nuisance or hazard to public health, welfare and the environment. |
Engineer | Form: (06 ) 402652794 4/22/2021 | Prior to starting plugging operations a bradenhead test shall be performed if there has not been a reported bradenhead test within the 60 days immediately preceding the start of plugging operations.
1) If, before opening the bradenhead valve, the beginning pressure is greater than 25 psi, sampling is required.
2) If pressure remains at the conclusion of the test, or if any liquids were present during the test, sampling is required.
The Form 17 shall be submitted within 10 days of the test. Sampling shall comply with Operator Guidance - Bradenhead Testing and Reporting Instructions. If samples are collected, copies of all final laboratory analytical results shall be provided to the COGCC within three (3) months of collecting the samples.
If there is a need for sampling, contact COGCC engineering for verification of plugging procedure. |
Engineer | Form: (06 ) 402652794 4/22/2021 | 1) Provide 48 hour notice of plugging MIRU via electronic Form 42.
2) After placing the shallowest hydrocarbon isolating plug (4332'), operator must wait a sufficient time to confirm static conditions. If at any time after placing this plug there is evidence of pressure or of fluid migration, contact COGCC engineering before continuing operations.
3) Prior to placing the shoe plug: verify that all fluid migration (liquid and gas) has been eliminated. If evidence of fluid migration or pressure remains, contact COGCC Engineer for an update to plugging orders.
4) After isolation has been verified, pump plug and displace. Cement to be circulated to surface if 7" casing is not pulled.
5) Leave at least 100’ of cement in the wellbore for each plug.
6) Properly abandon flowlines as per Rule 1105. Pursuant to Rule 911.a. Closure of Oil and Gas Facilities, Operator will submit Site Investigation and Remediation Workplans via Form 27 for COGCC prior approval before cutting and capping the plugged well, conducting flowline abandonment, and removing production equipment. Pursuant to Rule 1105.f. Abandonment Verification, within 90 days of an operator completing abandonment requirements for a flowline or crude oil transfer line, an operator must submit a Field Operations Notice, Form 42-Abandonment of Flowlines for on-location flowlines, and a Flowline Report, Form 44, for off-location flowlines or crude oil transfer lines.
7) With the Form 6 SRA operator must provide written documentation which positively affirms each COA has been addressed. |
Engineer | Form: (06 ) 402652794 4/22/2021 | Verify existing cement coverage by CBL - submit to COGCC for verification of plugging orders prior to continuing plugging operations. |
Engineer | Form: (06 ) 402652794 4/30/2021 | Squeeze at 428' to be performed in a manner that minimize damage to surface casing. |