| Engineer | Form: (06) 401385599 10/05/2017 | Prior to starting plugging operations a bradenhead test shall be performed.
1) If, before opening the bradenhead valve, the beginning pressure is greater than 25 psi, sampling is required.
2) If pressure remains at the conclusion of the test, or if any liquids were present during the test, sampling is required.
Sampling shall comply with Operator Guidance - Bradenhead Testing and Reporting Instructions. The Form 17 shall be submitted within 10 days of the test. |
| Engineer | Form: (06) 401385599 10/05/2017 | 1) Provide 48 hour notice of plugging MIRU via electronic Form 42.
2) Properly abandon flowlines as per Rule 1103.
3) Plug listed as half in-half out surface casing is actually a balanced production casing plug that will also cover the surface casing shoe. This plug must be tagged at 808’ or shallower. Leave at least 100’ of cement in the wellbore for each plug. |