Permit | Form: (02 ) 400205910 10/17/2011 | Water sampling req'd. Opr notified. Ready to pass pending public comment on 11/1/11. |
Engineer | Form: (06 ) 401858563 12/13/2018 | Operator shall implement measures to control venting, to protect health and safety, and to ensure that vapors and odors from well plugging operations do not constitute a nuisance or hazard to public welfare. |
Engineer | Form: (06 ) 401858563 12/13/2018 | 1) Provide 48 hour notice of plugging MIRU via electronic Form 42.
2) Prior to placing the 1,450' plug: verify that all fluid migration (liquid or gas) has been eliminated. If evidence of fluid migration or pressure remains, contact COGCC Engineer for an update to plugging orders.
3) After isolation has been verified, pump plug and displace. If cement is not circulated to surface, shut-in, WOC 4 hours then tag plug – must be at 1,074' or shallower and provide 10 sack plug at surface.
4) Leave at least 100’ of cement in the wellbore for each plug.
5) Properly abandon on-location flowlines as per Rule 1105. File electronic Form 42 once abandonment is complete. Within 30 days of an operator completing abandonment requirements for an off-location flowline or crude oil transfer line, the operator must submit a Flowline Report, Form 44.
|
Engineer | Form: (06 ) 401858563 12/13/2018 | If there has not been a reported Bradenhead test within 60 days of plugging this well, prior to starting plugging operations, a Bradenhead test shall be performed.
1) If, before opening the Bradenhead valve, the beginning pressure is greater than 25
psi, sampling is required.
2) If pressure remains at the conclusion of the test, or if any liquids were present during
the test, sampling is required.
3) If sampling is required contact COGCC engineering for an confirmation of plugging
requirements prior to placing any plugs.
Sampling shall comply with Operator Guidance - Bradenhead Testing and Reporting
Instructions.
The Form 17 shall be submitted within 10 days of the test.
|
Engineer | Form: (06 ) 402016610 4/24/2019 | Operator shall implement measures to control venting, to protect health and safety, and to ensure that vapors and odors from well plugging operations do not constitute a nuisance or hazard to public welfare. |
Engineer | Form: (06 ) 402016610 4/24/2019 | 1) Provide 48 hour notice of plugging MIRU via electronic Form 42.
2) Prior to placing the 1600' plug: verify that all fluid migration (liquid or gas) has been eliminated. If evidence of fluid migration or pressure remains, contact COGCC Engineer for an update to plugging orders.
3) After isolation has been verified, pump plug and displace. If cement is not circulated to surface, shut-in, WOC 4 hours then tag plug – must be at 1074' or shallower and provide 10 sack plug at surface.
4) Leave at least 100’ of cement in the wellbore for each plug.
5) Properly abandon on-location flowlines as per Rule 1105. File electronic Form 42 once abandonment is complete. Within 30 days of an operator completing abandonment requirements for an off-location flowline or crude oil transfer line, the operator must submit a Flowline Report, Form 44. |
Engineer | Form: (06 ) 402016610 4/24/2019 | The plug at 1630' with a CICR at 1600' needs to be placed and have an 8 hour WOC to assure that all fluid migration has been stopped. If that doesn’t isolate the flow, additional attempts in front of the surface shoe plug will need to be attempted. Other downhole potential squeeze opportunities may need to be looked at before the 1600' shoe plug. |
Engineer | Form: (06 ) 402016610 4/24/2019 | At the time of providing 48 hour notice of plugging MIRU via electronic Form 42, also contact via telephone:
Tom Peterson
Area (118) Field Inspector
tom.peterson@state.co.us
(970) 370-1281 (cell) |