| Engineer | Form: (06) 401343493 08/01/2017 | Prior to initiation of plugging operations, a Bradenhead test shall be performed. If there is 25# or greater present at the beginning of the test call COGCC Engineer for possible sampling requirements. Form 17 shall be submitted within 10 days. |
| Engineer | Form: (06) 401343493 08/01/2017 | 1) Provide 48 hour notice of plugging MIRU via electronic Form 42.
2) For 1750’ plug(surface casing): pump plug and displace. If plug not circulated to surface or falls back then tag plug – must be 400’ or shallower and provide 10 sx plug at the surface.
3) Properly abandon flowlines as per Rule 1103. File electronic Form 42 once abandonment complete.
|
| Engineer | Form: (06) 401343493 08/04/2017 | Documentation of previously set bridge plugs/cement set above Jsand, Codell and Niobrara must be included with the Subsequent Report of Abandonment. |