| Engineer | Form: (06) 401157695 12/14/2016 | 1) Prior to starting plugging operations a bradenhead test shall be performed. If the beginning pressure is greater than 25 psi, or if pressure remains at the conclusion of the test, or if any liquids were present contact COGCC Engineer for sampling requirements. The Form 17 shall be submitted within 10 days of the test.
2) Provide 48 hour notice of plugging MIRU via electronic Form 42.
3) Properly abandon flowlines as per Rule 1103. File electronic Form 42 once abandonment complete.
4) Indicated the well has a gyro from Sept. 2011 that has not been submitted to COGCC. Submit gyro survey data with Form 6 Subsequent Report of Abandonment.
5) Production casing stub plug is also surface casing shoe plug, this plug must be tagged at 892’ or shallower. Leave at least 100’ of cement in the wellbore for each plug. |
| Engineer | Form: (06) 401157695 12/14/2016 | Production records indicate this well has been SI since Jan. 2015 and no mechanical integrity test has been submitted to COGCC. Operator needs to ensure that this well will be plugged or have a mechanical integrity test within two years of the initial shut-in date.
|