Engineer | Form: (06 ) 400834825 5/7/2015 | 1) Submit Form 42 electronically to COGCC 48 hours prior to MIRU.
2) For 750’ plug: pump plug and displace. If cement is not circulated to surface, shut-in, WOC 4 hours and tag plug – must be 401’ or shallower and provide 10 sx plug at the surface. Leave at least 100’ of cement in the wellbore for each plug.
3) Properly abandon flowlines as per Rule 1103. Once flowlines are properly abandoned, file electronic form 42.
|