Permit | Form: (06 ) 401036644 5/13/2016 | Operator will provide update As-drilled GPS coordinates on the Form 6 Subsequent Report of Abandonment. |
Engineer | Form: (06 ) 401036644 5/13/2016 | No cement bond log on file with COGCC. Prior to plugging, operator must verify existing cement with a cement bond log. If CBL does not verify annular cement as presented, contact COGCC before proceeding. Submit CBL with Subsequent report of Abandonment. |
Engineer | Form: (06 ) 401036644 5/16/2016 | 1) Submit Form 42 electronically to COGCC 48 hours prior to MIRU.
2) For 600’ plug: pump plug and displace. If cement is not circulated to surface, shut-in, WOC 4 hours and tag plug – must be 195’ or shallower and provide minimum 10 sx plug inside and outside at the surface. Leave at least 100’ of cement in the wellbore for each plug.
3) Properly abandon flowlines. Once flowlines are properly abandoned, file electronic form 42.
|