COGIS - Conditions of Approval Results
TypeSource DocumentConditions of Approval
PermitForm: (06 )
401959964
3/18/2019
Submit Operator's Monthly Production Reports (Form 7) required for compliance with Rule 309 within 30 days. •D Sand production was never reported; should be reported from October of 2006 - present
EngineerForm: (06 )
401959964
3/19/2019
Operator shall implement measures to control venting, to protect health and safety, and to ensure that vapors and odors from well plugging operations do not constitute a nuisance or hazard to public welfare.
EngineerForm: (06 )
401959964
3/19/2019
1) Provide 48 hour notice of plugging MIRU via electronic Form 42. 2) Prior to placing the 260' plug: verify that all fluid migration (liquid or gas) has been eliminated. If evidence of fluid migration or pressure remains, contact COGCC Engineer for an update to plugging orders. 3) After isolation has been verified, pump plug and displace. If cement is not circulated to surface, shut-in, WOC 4 hours then tag plug – must be at 160' or shallower and provide 10 sack plug at surface. 4) Leave at least 100’ of cement in the wellbore for each plug. 5) Properly abandon on-location flowlines as per Rule 1105. File electronic Form 42 once abandonment is complete. Within 30 days of an operator completing abandonment requirements for an off-location flowline or crude oil transfer line, the operator must submit a Flowline Report, Form 44.
EngineerForm: (06 )
401959964
3/19/2019
If there has not been a reported Bradenhead test within 60 days of plugging this well, prior to starting plugging operations, a Bradenhead test shall be performed. 1) If, before opening the Bradenhead valve, the beginning pressure is greater than 25 psi, sampling is required. 2) If pressure remains at the conclusion of the test, or if any liquids were present during the test, sampling is required. 3) If sampling is required contact COGCC engineering for a confirmation of plugging requirements prior to placing any plugs. Sampling shall comply with Operator Guidance - Bradenhead Testing and Reporting Instructions. The Form 17 shall be submitted within 10 days of the test.
EngineerForm: (06 )
401959964
3/19/2019
Perf at 2500' and pump 40 sacks leaving 10 sacks in the casing. Move the plug at 700' down to 1050' and set CICR at 1000' and cement with 24 sacks. Operator in agreement.
 
COGIS - Best Management Practice Results
No records to display.