Skip to Main Content

COGIS DB

 
Facility TypeFacility ID/
API
Facility Name/
Number
Operator Name/
Number
StatusField Name/
Number
LocationLocation IDRelated Facilities
WELL05-103-10663PICEANCE CREEK UNIT
T75X-3G8
QB ENERGY OPERATING LLC
10844
SI
1/1/2026
PICEANCE CREEK
68800
RIO BLANCO  103
NESE 3 2S97W 6
335695View Related
 
COGIS - Conditions of Approval Results
TypeSource DocumentConditions of Approval
EngineerForm: (04)
403180100
08/04/2023
1) Operator shall comply with COGCC Rule 419. Bradenhead Monitoring, Testing, and Reporting and Rule 420. Form 17, Bradenhead Test Report 2) At least once a year shut in bradenhead for 7 days or until the pressure reaches the bradenhead threshold and perform a bradenhead test. Report results on a Form 17, as specified in Rule 420 or other Director approved submittal method. 3) Complete installation of BH monitoring system by 11/23/2023 4) Within 30 days of completing the work, submit a Form 4 Subsequent Report - Bradenhead Plan
 
COGIS - Best Management Practice Results
No records to display.