WELL05-103-10192PICEANCE CREEK UNIT
F27X-8G
QB ENERGY OPERATING LLC
10844
PR
1/1/2026
PICEANCE CREEK
68800
RIO BLANCO  103
SWSW 8 2S95W 6
316299View Related
 
COGIS - Conditions of Approval Results
TypeSource DocumentConditions of Approval
EngineerForm: (04)
403194264
11/16/2022
1) Operator shall comply with COGCC Rule 419. Bradenhead Monitoring, Testing, and Reporting and Rule 420. Form 17, Bradenhead Test Report 2) At least once a year shut in bradenhead for 7 days or until the pressure reaches the bradenhead threshold and perform a bradenhead test. Report results on a Form 17, as specified in Rule 420 or other Director approved submittal method. 3) Within 30 days of completing the work, submit a Form 4 Subsequent Report - Bradenhead Plan 4) Submit a current WBD on a Form 4 Sundry “COMPLIANCE with CONDITION OF APPROVAL (COA)” by 02/31/23 5) Complete installation of BH monitoring system by 3/31/2023 4) Perform diagnostics, source and causal factors for high Intermediate pressures and report results on Sundry required by COA#3
 
COGIS - Best Management Practice Results