Engineer | Form: (04 ) 401182424 2/28/2018 | This approval is good for one year and a new application must be made before January 11, 2018(1 year from prior application). Updates for the planned utilization of the well should be included with the application. A Form 5A is required to report all plugs currently downhole which isolate the perforated interval. |
Engineer | Form: (04 ) 401510481 2/28/2018 | This approval is good for one year and a new application must be made before January 11, 2019(1 year from prior application). Updates for the planned utilization of the well should be included with the application. A Form 5A is required to report all plugs currently downhole which isolate the perforated interval. |
Engineer | Form: (04 ) 401627368 5/18/2018 | This approval is good for one year and a new application must be made before May 2, 2019(1 year from prior application). Updates for the planned utilization of the well should be included with the application.
A Form 5A is required to report all plugs currently downhole which isolate the perforated interval.
The Form 7 reporting must reflect the well status dates reported on the Form 4-TA request. |
Engineer | Form: (04 ) 401868241 4/15/2019 | This approval is good for one year and a new application must be made before May 2, 2020(1 year from prior application). Updates for the planned utilization of the well should be included with the application.
A Form 5A is required to report all plugs currently downhole which isolate the perforated interval. |
Engineer | Form: (04 ) 402266941 3/26/2020 | 1) This approval is good for one year and a new application must be made before 1/9/2021 (1 year from prior application). Updates for the planned utilization of the well should be included with the application.
2) The Form 7 reporting must reflect the well status dates reported on the Form 4-TA request.
3) A Form 5A is required to report all plugs currently downhole which isolate the perforated interval.
|
Engineer | Form: (04 ) 402551554 4/19/2021 | 1) This approval is good for one year and a new application must be made before 01/09/2022 (1 year from prior application). Updates for the planned utilization of the well should be included with the application.
2) The Form 7 reporting must reflect the well status dates reported on the Form 4-TA request.
|
Engineer | Form: (04 ) 402905364 2/2/2022 | 1) This approval is good for one year and a new application must be made before 01/09/2023 (1 year from prior application). Updates for the planned utilization of the well should be included with the application.
2) The Form 7 reporting must reflect the well status dates reported on the Form 4-TA request. Please update production reporting status of all applicable months from SI to TA for 1/1999 forward. COGCC digital production reporting began in 1999 and does not go back to 1995.
3) Submit a current Wellbore Diagram on a Form 4 Sundry
|